A project is enabled for Burdening by setting up a burden schedule at the project type level. A Miscellaneous expenditure Item Is charged to the project with a raw cost of $100 and expenditure type "Overhead." The "Overheads" expenditure type is excluded from all cost bases in the burden structure.
What happens when the "PRC: Distribute usage and Miscellaneous Costs" program is run for this project?
A. The program errorswith the message "Missing Expenditure type."
B. The program completes successfully; Raw Cost = $100, Burden Cost=$0,TotalBurdened cost=$100.
C. Theprogram completes successfully; Raw Cost=$100, Burden Cost= $100,TotalBurdened cost=$100.
D. Theprogram completes successfully; Raw Cost =$100, Burden Cost=$0, Total Burdened cost= $0.
A US-based company is providing resources to a UK subsidiary and has implemented Oracle Projects intercompany billing solutions. How would the US company create the Accounts Payable invoice in the UK operating unit?
A. when the draft intercompany invoiceis approvedin the us Projects ledger
B. when the draftintercompanyrevenue is approved in the US Projectsledger
C. Invoice automatically createdas part of the PRC: Tieback Invoices fromReceivables in the USProject ledger
D. when the draftintercompanyinvoice is released in the US Projects Ledger
E. on creation ofthe Intercompany revenue in the US General Ledger
Company ABC wants to deploy workplan task structures where the lowest tasks represent deliverables. They want to collect costs at a level higher than the lowest tasks for groups of deliverables. Which two task structure relationships are available for them to consider?
A. Define the structures as Fully Shared.
B. Utilize Task-based mapping structures.
C. Defineaseparate branch of task hierarchy for deliverables.
D. Define a separate branch of task hierarchy for cost collection.
E. Definethe structures as Partially shared.
A project is undertaken for a customer where all labor costs are non-billable, and Non-Labor costs are billable if the accumulated costs incurred are greater than $10k. How can Oracle Projects be implemented to support this?
A. Use transaction controls to restrict billing to Non-Labor elements and to calculate the bill amounts on Non-Labor.
B. Use transaction controls tobilling Non-Labor elements, capture the value on the project, and then use the Non-Labor billing extension to calculate when an activity is billable.
C. Create an agreement and funding for $10k only, and fund only those tasks on a project where you estimate to incur costs of $10k or more.
D. Use the cost-to-cost billing extension to build billing rules to meet the requirement.
E. Use the cost accrual extension.
An organization posts project costs to the balance sheet as they are incurred. Each month they recognize project revenue on each project.
Select the option that ensures that costs are credited from the balance sheet and debited to profit and loss as revenue is recognized.
A. Use events for project revenue and use GL journals to carry outthe relevant account postings.
B. Implement a projectrevenue extensionwithappropriate event types and AutoAccountingdefinition.
C. Usemiscellaneoustransactions to generate revenue with the appropriate AutoAccountingdefinition.
D. Use preapproved batches with a class type of "Work in Process" to generate revenue withthe appropriate AutoAccounting definition.
A customer has two operating units: US and Ireland. A project that is set in the Ireland operating unit requires the services of employees from the US operating unit.
Identify three mandatory steps that must be completed for the employees in the US to enter their time on the project and for costs to be successfully distributed.
A. Set up Internal Billing Implementation optionsin US and Ireland.
B. Define providercontrolsin US and receiver controlsin Ireland.
C. Setup a new transaction source to receive Intercompany transactions in Ireland.
D. For theprojectinIreland, select "Allow Cross Charges to all Operating Units within Legal Entity".
E. For the projectin Ireland,set up transaction controls to allow charges from other operating units.
A customer has gone into bankruptcy and is unable to pay their bills. This means that the project revenue is now overstated. How can the customer reduce the revenue on the project to accurately reflect the amount of collectable revenue?
A. Create a revenue write-off event forthe uncollectable element andinterface to General Ledger.
B. Create a negative funding line and assign to the project thus reducing its revenue.
C. Createacost adjustment on the project using preapproved batches.
D. Createa credit memo in Oracle Projects and interface to Accounts Receivable.
E. Entera transaction control against the expendituretypes and regenerate the draft invoice.
What must be defined to enable a company to use an organization for a straight time expenditure?
A. Define the organization with the Following:1. Add Cost Centreas the Organization type.2. Add an organization classification ofHR Organization.3. Add the organizationto anorganization hierarchy.
B. Define the organization with the Following:1. Add the organization classifications HR Organization and ProjectExpenditure/Event2.Add the organization to anorganizationhierarchy3. Add the organization hierarchy to the appropriate Oracleprojectimplementation option setting
C. Define the organization with the following:1.Add the organization classificationsProject/Task Owning Organization and ProjectExpenditure/Event Organization.2. Add the organization to an organization hierarchy.3.Add the organization hierarchy to the appropriate Oracle project implementation option setting.
D. Define the organization with the following:1. Add the organization classifications Project Expenditure/Event Organization.2. Add the organization to an organization hierarchy.3.Add the organization hierarchy to the appropriate Oracle project implementation option setting.
E. Define the organization with the Following:1. Add the organization classifications HR Organization and ProjectExpenditure/Event2. Add the organization to an organization hierarchy.3. Define Organization Labor Costing Rules.
Identify three adjustment actions that require submission of Distribute costs program to process the adjustments?
A. Change Comment
B. Release Hold
C. Split
D. Transfer
E. Recalculate Revenue
F. Capitalizable to Non-Capitalizable
Which three types of People Resources does Oracle Projects support?
A. Team Roles
B. Straight Time
C. Jobs
D. Item
E. Named Person
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-511 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.