  • Question 61:

    What is the definition of a project outcome?

    A. A measurable improvement that is perceived as an advantage by one or more stakeholders

    B. The reason for the project

    C. The result of the change derived from using the project's outputs

    D. The project's specialist products.

  • Question 62:

    What is defined as a temporary organization that is created for the purpose of delivering one or more business products?

    A. Corporate or programme management

    B. A project

    C. A product breakdown structure

    D. A user group

  • Question 63:

    Which is an objective of the Managing Product Delivery process?

    A. Sign-off completed Work Packages

    B. Ensure the Business Case is kept under review

    C. Report progress to the Project Board

    D. Ensure that work on products is authorized and agreed with the team

  • Question 64:

    Which product is NOT created in the Managing a Stage Boundary process?

    A. Benefits Review Plan

    B. End Stage Report

    C. Lessons Report

    D. Exception Plan

  • Question 65:

    Which is NOT an objective of the Controlling a Stage process?

    A. Implement actions to control the impact of risks that occur during the stage

    B. Review the Business Case at regular intervals to assess the impact of changes that occur during the stage

    C. Update the Business Case with any changes agreed with the Project Board

    D. Coordinate the delivery of products as agreed in the Stage Plan

  • Question 66:

    If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

    A. Checkpoint Report

    B. Highlight Report

    C. Highlight Report

    D. Product Status Account

  • Question 67:

    Which is an objective of the quality review technique?

    A. To baseline a product

    B. To provide a common understanding of what products a project will create

    C. To define the quality methods required within a project

    D. To determine the quality responsibilities of a project team

  • Question 68:

    Which is a difference between management and technical stages?

    A. Management stages require planning and technical stages do not

    B. Technical stages can overlap and management stages cannot

    C. Management stages deliver products and technical stages do not

    D. Technical stages require resources and management stages do not

  • Question 69:

    Which describes the 'Identify Risks' step within the recommended risk management procedure?

    A. Identify responses to risks documented in the Business Case

    B. Gather information about the project environment and objectives

    C. Identify the roles to be involved in risk management activities

    D. Identify uncertainties that may impact on the delivery of the project objectives

  • Question 70:

    Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?

    A. Business Case

    B. Plans

    C. Progress

    D. Quality

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.