In a stateless Auto Deploy design, which of the following is correct?
A. The vCenter has a direct impact in the event of an outage of this component.
B. The Auto Deploy server has a direct impact in the end of an outage of this component.
C. Both of the above statements are correct
A(n) _____________ is an item that is taken to be true in the design phases but has not been tested prior to execution.
A. requirement
B. constraint
C. assumption
D. risk
You are a virtualization consultant working on a DR project. You have proposed a solution that uses SAN replication technology to replicate production virtual machine files. This meets the cold standby requirement.
Which of the following could be a design constraint?
A. The hardware currently being used in the datacenter is out of support.
B. The company is undecided about the choice of centralized storage to be used in the enterprise.
C. The company is at the end of year 1 of a 3-year contract for the point-to-point link between Site A and Site
D. This link is currently 10 MB.
A best practice can change over time.
A. True
B. False
Only a software vendor develops a standard process or configuration.
A. True
B. False
A logical design can contain which of the following? (Choose three)
A. BIOS settings
B. Data flow
C. Key component relationships
D. High-level diagrams
E. Server host names
You are a VMware architect employed to design and build application environments and the underlying platform for a software development company. The company is using a "devops" approach and has engaged with you at the beginning of the first planning meeting/pre-sprint. The software has yet to be written. However, you have some high-level specifications that are subject to change at each of the early meetings.
The ______ is more logical for virtual machine sizing.
A. predictive sizing approach based on current software
B. adaptive sizing approach
You are working on a hybrid cloud project, where production applications (yet to be fully developed) are to be deployed. Which of the following is a project requirement?
A. The production data must be in the UK at all times.
B. The hosting partner provides sufficient resources without overcommitment to support application load.
C. The hosting provider meets uptime expectations.
D. The development team provides the software on time.
In the project life cycle, the ____________ defines the vision.
A. IT architect
B. software vendor
C. business
Based on the information in the high-level design extract from question 2, what storage protocol is unsuitable?
A. NFS
B. iSCSI
C. FC
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only VMware exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your VCAP5-DCD exam preparations and VMware certification application, do not hesitate to visit our Vcedump.com to find your solutions here.