  • Question 31:

    What activity do you perform during the daily stand-up meeting?

    A. Provide end users with a demo of the new features

    B. Re-baseline the release plan

    C. Report showstoppers.

    D. Negotiate acceptance criteria

  • Question 32:

    A customer with an existing SAP S/4HANA solution is exploring the best approach to move their landscape into the cloud.Which is the most suitable option for the customer?

    A. Mix and Match

    B. System Conversion

    C. Selective Data Transition

    D. Lift and Shift

  • Question 33:

    What technique helps a Scrum team to prioritize a large, flat backlog?

    A. Planning poker

    B. Retrospective

    C. User story mapping

    D. Fit-gap analysis

  • Question 34:

    Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question.

    A. Design to-be business process models

    B. Review Best Practices process flow

    C. Document integration requirements

    D. Enable customers on standard business processes

  • Question 35:

    For which of the following products do you find a specific set of best practices for the public sector?

    A. SAP S/4HANA

    B. SAP SuccessFactors Employee Central

    C. SAP Marketing Cloud

    D. SAP S/4HANA Cloud, public edition

  • Question 36:

    Which activity helps the project team identify and add user stories to the backlog?

    A. Planning the User Acceptance Testing

    B. Conducting the fit-to-standard workshop

    C. Preparing a project schedule and budget

    D. Assessing project risks and issues

  • Question 37:

    You are defining the testing strategy for your project.What would you include in a Scope of Integration test?

    A. The functionality of end-to-end business processes

    B. The network communication

    C. The functionality of modular processes

    D. The connectivity between database and application servers

  • Question 38:

    What is the correct order of the SAP Activate methodology phases?

    A. Discover > Prepare > Explore > Realize > Deploy > Run

    B. Plan > Build > Run > Sustain

    C. Plan Design > Build > Operate

    D. Prepare > Discover > Explore > Realize > Deploy > Run

  • Question 39:

    Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path?

    A. Solution Validation and Delta Design

    B. Fit-to-standard

    C. Simplification and Custom Code Impact Analysis

    D. Setup and Enablement

  • Question 40:

    What is the objective of a sprint retrospective meeting?

    A. Improve the Scrum process.

    B. Provide formal feedback to the Project Manager.

    C. Define the stakeholder management approach

    D. Review and prioritize the backlog.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_ACT_2403 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.