What is the basis for approving work results (signing act of acceptance) on a project phase level?
A. Definition of done for user story
B. Scrum of scrums meeting decision
C. Definition of ready for sprint
D. Agreed and met acceptance criteria within quality gate
What is the most granular level of the methodology you can view in the SAP roadmap viewer?
A. Task
B. Deliverables
C. Scenario
D. Phase
What are deliverables of the Application: Integration work stream in the prepare phase?
There are 3 correct answers to this question.
Response:
A. Fit/Gap Analysis
B. Data Cleansing
C. Security Checks
D. Adaptation Specifications
E. Network Connectivity Checks
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables across the project phases?
Please choose the correct answer.
Response:
A. a) Code adjustment b) Detailed System Assessment c) Production Readiness Check d) Validation of Migration
B. a) Production Readiness Check b) Detailed system Assessment c) Code Adjustment d) Validation of Migration
C. a) Detailed system Assessment b) Code Adjustment c) Validation of Migration d) Production Readiness Check
D. a) Detailed system Assessment b) Production Readiness Check c) Code Adjustment d) Validation of Migration
Which of the following is a Key Deliverable of the Prepare phase?
Please choose the correct answer.
Response:
A. Solution Scope and Value Determination
B. Change Impact Analysis and Communication Plan
C. Baseline Build
D. Release and Sprint Plan
What is the best transition scenario for a customer looking for some, but not full process redesign, and reuse of existing processes in some areas that still fit?
A. Selective Data Transition
B. New Implementation
C. System Conversion
Which of the following are components of SAP Model company? There are 3 correct answers to this question.
A. Quality gate checklist
B. Accelerators
C. Business-driven configuration questionnaire
D. Business process content for SAP solution manger
E. Preconfigured solution
How many countries can be activated at a time?
A. 3
B. 2
C. 1
D. 4
Which new project roles are introduced with the SAP Activate Agile methodology?
There are 2 correct answers to this question.
Response:
A. SCRUM Master
B. Product Owner
C. Integration Lead
D. Design Thinking Coach
What are some extension item types can be transported from the Quality system to the Production system?
A. Form Templates
B. Custom Fields
C. Communication Arrangements
D. Master Data
E. Query Designer Report
F. Employee Data
G. Custom Business Logic
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_ACTIVATE12 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.