  • Question 91:

    How can you differentiate stock quantities within a plant in inventory management?

    Please choose the correct answer.

    A. Bin locations

    B. Storage locations

    C. Storage area

    D. Shipping points

  • Question 92:

    In which sequence does the system search for a valid source of supply when you manually create a purchase requisition with automatic source determination?

    Please choose the correct answer.

    A. Info record Outline agreement item Source list Quota arrangement

    B. Source list Outline agreement item Info record Quota arrangement

    C. Quota arrangement Source list Outline agreement item Info record

    D. Info record Source list Outline agreement item Quota arrangement

  • Question 93:

    What are some available SAP Smart Business key performance indicators (KPIs) for contracts? There are 3 correct answers to this question.

    A. Unused contracts

    B. Contract leakage

    C. Conditions by contract

    D. Contract release orders

    E. Value contract consumption

  • Question 94:

    You have to post scrap expenses to a special account. Based on which characteristics can you influence the behaviour of the account determination?

    There are 2 correct answers to this question.

    A. Storage location

    B. Stock type

    C. Plant

    D. Movement type

  • Question 95:

    What are some key features of the SAP Smart Business key performance indicators (KPIs) tiles used for purchasing analytics?

    There are 2 correct answers to this question.

    A. Each tile represents a set of actionable cards.

    B. Chart snippets on a tile are updated after each start of the evaluation.

    C. The tiles show key information that is updated in real time.

    D. Numbers on the tiles can have different colours to represent different thresholds of alert.

  • Question 96:

    Goods from a supplier arrive at your warehouse. However, you do NOT want these goods to be part of your inventory yet. What is the procedure for recording the conditional goods receipt (GR)?

    Please choose the correct answer.

    A. Make a note in the purchase order and wait until the conditions for accepting the delivery are met.

    B. Post a goods receipt to non-valuated GR blocked stock.

    C. Post a goods receipt to valuated GR blocked stock.

    D. Select the blocked stock type when posting the goods receipt.

  • Question 97:

    What are some options when working with scheduling agreements? There are 3 correct answers to this question.

    A. A scheduling agreement item is always plant-specific.

    B. A scheduling agreement can be used for a consignment process.

    C. Item category M (Material unknown) can be used in a scheduling agreement.

    D. A material master record is optional in a scheduling agreement item.

    E. Scheduling agreement delivery schedule lines can only be created manually.

  • Question 98:

    Which of the following activities is a prerequisite to enable partner roles determination in purchasing documents?

    Please choose the correct answer.

    A. Assign a partner schema to relevant account groups.

    B. Assign a partner schema to relevant purchasing document types.

    C. Assign a partner role to relevant purchasing document types.

    D. Assign a partner schema to relevant arrangement types.

  • Question 99:

    Which of the following are features of the Delivery Completed indicator in a purchase order (PO) item? There are 2 correct answers to this question.

    A. If you set the indicator, the PO item is NO longer relevant for material requirements planning.

    B. If you set the indicator, NO further goods receipt may be posted for the PO item.

    C. The indicator is always set automatically if the quantity received is within the under delivery tolerance.

    D. You can set the indicator manually when entering a goods receipt for your PO item.

  • Question 100:

    Which of the following CANNOT be created by MRP Live? Please choose the correct answer.

    A. Planned order.

    B. MRP list

    C. Purchase requisition

    D. Schedule line

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS452_2020 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.