Exam Details

  • Exam Code
    :DASSM
  • Exam Name
    :Disciplined Agile Senior Scrum Master (DASSM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :193 Q&As
  • Last Updated
    :Apr 01, 2025

PMI PMI Certifications DASSM Questions & Answers

  • Question 121:

    A team has completed the work in their iteration backlog earlier than expected. There's still three days left of the iteration, what should the team do now?

    A. Work on noncritical tasks until the product owner can them more work.

    B. Wait for the other groups to complete their work prior to doing anything else.

    C. Work with the product owner to pull more work from the product backlog into their iteration backlog.

    D. Report the differences in completion time so the next iteration can be planned more efficiently.

  • Question 122:

    When would you adopt the Continuous Delivery Lean life cycle?

    A. We have an experienced team working on a product or service where the requirements will evolve at a reasonable pace

    B. We have an experienced team working on a product or service where the requirements change frequently, potentially daily

    C. All of the above

    D. We have team that is new to Lean working on a product or service where the requirements change frequently, potentially daily

    E. We have team that is new to Lean working on a product or service where the requirements will evolve at a reasonable pace

  • Question 123:

    True or False: Delight customers as a principle means never to exceed expectations of the customers but to just about meet them

    A. True

    B. False

  • Question 124:

    Which of the following is not one of the reasons that Disciplined Agile teams practice transparency?

    A. Everybody knows what is happening

    B. It improves team morale

    C. It delays breaking bad news to customers

    D. Customers appreciate and expect transparency

  • Question 125:

    Using Lean thinking, we should be managing

    A. The value stream

    B. Each step of the work

    C. Our people

    D. By letting people figure out what they need to do

  • Question 126:

    Which of the following milestones represent a DA project moving from Construction to Transition stage?

    A. Production ready

    B. Sufficient functionality

    C. Proven architecture

    D. Continued viability

    E. Stakeholder vision

  • Question 127:

    Which of the following is not a role for the team lead in a Disciplined Agile team?

    A. Guiding the team through improvement actions

    B. Helping the team collaborate

    C. Providing timely decisions on priority and product roadmap

    D. Helping the team evolve their WoW

  • Question 128:

    Which of the following is one of the 4 views of Disciplined Agile?

    A. Mindset

    B. Enterprise

    C. Technology

    D. Goals

  • Question 129:

    Which is not a feature of a user story?

    A. Achievable

    B. Estimable

    C. Testable

    D. Negotiable

  • Question 130:

    Which of the following is an advantage of a project team as opposed to long standing product teams?

    A. Greater motivation to learn and evolve the WoW

    B. Greater focus on delivery and short term goals

    C. Creates a long term focus

    D. Brings work to the team rather than team to the work

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your DASSM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.