In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?
A. Prepare
B. Explore
C. Deploy
D. Realize
What does the side-by-side extensibility option mean?
A. Extensibility based on the SAP cloud platform and published APIs
B. Transfer reporting to BW/4HANA
C. Context-aware SAP S/4HANA extensions, focused on tight integration
D. Have two SAP S/4HANA instances-one for standard code, and another for customer developments
What is the purpose of the scrum board?
A. To manage the resource load
B. To show the functional breakdown of the solution scope
C. To document the results of the integration test
D. To visualize team progress
In which phase of the SAP Activate Methodology does the team complete the System Assessment?
A. Explore
B. Deploy
C. Prepare
D. Realize
What is strategy level 0 (L0) artifact?
A. Project resulte that is developed solely by the partner
B. Approach document that is developed by a united project team (partner + customer)
C. Optional information that is NOT important for project activities
D. Preliminary strategy developed by the customer to approach the project in a specific area
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? (Choose 2)
A. Run SAP Like a Factory
B. Always Connected
C. Intelligent Enterprise
D. Build SAP Like a Factory
What are the substreams in the Data Management Workstream? (Choose 3)
A. Data migration
B. Master data management
C. Data volume management
D. Data aging
How does SAP Cloud ALM provide guidance for implementation steps?
A. Resource planning
B. Preloaded content that adheres to SAP Activate tasks
C. Project management timelines
D. Documentation management
In SAP Activate, what tool is used in the during the Realize phase to make forecasts based on actual data?
A. Release Plan
B. Burndown Chart
C. Project Plan
D. Product Increment
What do you do during post cutover?
A. Perform Technical System Test
B. Perform the Verification Session of the SAP Going Live Check
C. Conduct Organizational Readiness Check
D. Setup Operational Support
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your E_ACTCLD_23 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.