Exam Details

  • Exam Code
    :ISTQB-TAE
  • Exam Name
    :ISTQB Certified Tester Advanced Level-Test Automation Engineering
  • Certification
    :Test Automation Engineering
  • Vendor
    :BCS
  • Total Questions
    :79 Q&As
  • Last Updated
    :Dec 12, 2024

BCS Test Automation Engineering ISTQB-TAE Questions & Answers

  • Question 1:

    Which of the following is NOT an advantage of test automation?

    A. The ability to perform tests which would be difficult or impossible to execute manually

    B. The ability to run more tests in less time and therefore to make it possible to run them more often

    C. The ability to find more defects with the same tests, compared to executing the same test manually

    D. The ability to enable a better use of skilled testers by freeing them from repetitive and boring tasks

  • Question 2:

    Which of the following success factors for a test automation project is TRUE?

    A. Automated tests must be designed to capture only the data that is strictly needed for comparing expected and actual results

    B. The test cases to be automated first must always be selected based on the number of times a test will need to be run

    C. The test cases to be automated must have a high dependency on particular data values

    D. Automated tests that fail due to changes in the requirements of the SUT should be promptly fixed rather than disabled from the test suite

  • Question 3:

    A defect in a SUT has been resolved and validated by an automated defect re-test in the current release of the software. This retest has now been added to the automated regression test suite.

    Which statement BEST describes a reason why this defect could re-occur in future releases?

    A. Automated defect confirmation testing is not effective at confirming that the resolved defect will continue to work in future releases

    B. The configuration management process does not properly control the synchronization between software archives

    C. The automated regression test suite is not run consistently for future releases.

    D. The automated regression test suite has a narrower scope of functionality

  • Question 4:

    You are a TAE working for a software house which provides quarterly releases of its software to its customers. There are many different versions of the SUT that need to be tested simultaneously by different tests teams.

    Your TAS is complex and you need to ensure it remains consistent across the different SUT environments. What is the BEST and MOST efficient way to ensure each of the test teams use the same version of the TAS to test the different versions of the SUT?

    A. Due to the complexities involved and the high risks associated with these releases, it would be best to revert to manual testing.

    B. Produce comprehensive documentation of the TAS, installation and usage guidelines and provide training for each team member.

    C. Install the TAS is a central repository and have an automated installation and configuration of the TAS from this repository to each of the SUT environments.

    D. Develop a tool to track historical test results across the different SUT environments and look for trends.

  • Question 5:

    Consider the following example of TAS metrics.

    Time to execute automated tests

    Speed and efficiency of TAS components

    Which of the following statements is TRUE?

    A. A and B are both internal TAS metrics

    B. A is an internal TAS metric and B is an external TAS metric

    C. A and b are both external TAS metric

    D. A is and external TAS metric and b is an internal TAS metric

  • Question 6:

    Which of the following is NOT a technical design consideration for a TAA?

    A. The number of users for the SUT

    B. Availability of interfaces for the SUT to be testable

    C. Standards and Legal requirements, e.g data privacy

    D. Data used by the SUT, e.g configuration, users

  • Question 7:

    You are testing a major enhancement to an air traffic control user interface. You have use of a sophisticated pre-production test environment, created specifically for large scale automated regression, performance and security testing. The window for regression testing is limited and must successfully conclude, with no major regressions remaining, before the non-functional testing starts.

    You have been using the same version of the TAS for the last few releases, each time completing the automated regression test suite in a single overnight run. However, due to the latest enhancements for the SUT, you believe there is a risk that the test suite may no longer complete overnight and therefore delay performance and security testing.

    Which option would be the BEST and MOST cost-efficient approach to mitigate this risk?

    A. Create a mirror of the pre-production test environment and split the regression test suite to run in parallel across the environments.

    B. Split the regression test suite into multiple parts, running in the environment across consecutive nights.

    C. Analyse the regression test suite and remove test coverage duplication and redundancy.

    D. Introduce better coding practices for the automation scripts, including coding guidelines, reviews and improved static analysis.

  • Question 8:

    Which of the following is an important success factor for any significant automation project?

    A. The TAA must be designed for testability.

    B. The TAA is self-documenting

    C. The SUT must be designed for testability

    D. The SUT is self-documenting

  • Question 9:

    You are working on a TAS for standalone application. The automated tests are developed based on a automation framework that allows interaction with GUI elements using on object orientated API. The GUI elements include menus, buttons,

    radio buttons, text toolbars and their properties.

    Whilst automating a test, you have discovered that the GUI elements of some third party components are not identifiable by the automated tool you are using.

    Which of the following is the FIRST step that you take to investigate this issue?

    A. Verify the testability support with the providers of the third party components

    B. Verify whether the GUI identification depends on the browser.

    C. Adopt an approach that uses the coordinates of the GUI elements instead

    D. Verify whether naming standards for variables and have been defined for the current automation solution

  • Question 10:

    New features have been added for the current release of a SUT.

    Which action would NOT be appropriate for the TAE to perform when evaluating the impact on the TAS?

    A. Gather feedback from the Business Analysts to determine if the current TAS will meet the needs of the new features.

    B. Review existing keywords to see if they need to be modified.

    C. Run existing automated tests against the updated SUT to verify and record any changes to their correct operation.

    D. Evaluate compatibility with existing test tools and, where necessary, identify alternative solutions.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only BCS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISTQB-TAE exam preparations and BCS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.