Why should MoV align with an organisation's objectives?
A. To minimise the costs of delivering the project
B. To maximise benefits arising from the project
C. To meet stakeholder expectations
D. To avoid maximising value within one project that could diminish value across the wider programme
Which of the following cost types would be considered in calculating discounted cash flow?
1.
Capital or one off costs
2.
Periodic maintenance costs
3.
Regular operational costs
4.
Opportunity costs
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2,3, 4
How is a function described in Function Analysis in MoV?
A. Verb only
B. Adjective and verb
C. Verb and noun
D. Adjective and noun
Which is a key component of the Evaluate and Select process?
A. Initial briefing meeting
B. Team selection
C. Resource analysis
D. Idea selection
Which is one stage in the approach to MoV implementation?
A. Understand and articulate value
B. Tailor MoV activity to suit the subject
C. Frame the programme or project
D. Apply MoV throughout the investment decision
Which statement about a decision building meeting is true?
A. It should be chaired by the senior responsible owner.
B. The owner, responsible for implementation, has already been determined by the MoV team before the meeting.
C. Decisions from the meeting should form the basis of the proposal implementation plan
D. Attendees should be limited to the senior responsible person, project manager and project sponsor
What is the principal output from allocation to categories and the idea selection matrix?
A. A list of rejected ideas
B. A list of ideas or options that should be developed further
C. Plans to develop selected ideas into value improving proposals D. Approved value improving proposals
Which is NOT a reason why it becomes more difficult to implement changes identified by a MoV Study as a project progresses?
A. Sunk costs increase as a project progresses
B. Project team members gain increased ownership of their work
C. Resistance to change increases
D. Project objectives are less clear
Who should be responsible for developing a value-improving proposal?
A. The MoV team as a whole
B. The most relevant functional manager
C. The allocated owner of the value improving proposal
D. A technical expert nominated by the allocated owner
Which three criteria explain why the MoV individual competence model is useful to an organisation?
1.
To assess an individual's capabilities and the type of MoV study for which they are suited.
2.
To recognise that a fully but recently qualified practitioner will lack the experience to undertake studies on particularly complex projects.
3.
To enable recently qualified practitioners to learn to undertake MoV where human and cultural factors may be significant.
4.
To allow recently qualified practitioners to undertake studies on particularly complex projects.
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MOVF exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.