Complete the following sentence.
In the ADM, documents which are under development and have not undergone any formal review and approval process are called _________. Documents which have been reviewed and approved are called ___________.
A. “concept” - “deliverable”
B. “draft” - “approved”
C. “Version 0.1” - “Version 1.0”
D. “draft”- “finalized”
Which of the following does the TOGAF standard describe as a package of functionality defined to meet business needs across an organization?
A. An application
B. A solution architecture
C. A building block
D. A deliverable
Consider the graphic illustrating a method supporting the TOGAF ADM.
What does the method help identify?
A. Architecture Solutions
B. Business Scenarios
C. Solution Building Blocks
D. Alternative Target Architectures
Consider the diagram showing a classification model for Architecture Landscapes.
What are the items labelled A, B and C?
A. A-Corporate Capability, B-Portfolio Capability, C-Project Capability
B. A-Architecture Vision, B-Business Architecture, C-Architecture Development
C. A-Strategy Architecture, B-Tactic Architecture, C-Operational Architecture
D. A-Capability Architecture, B-Segment Architecture, C-Enterprise Strategic Architecture
Complete the sentence. The four purposes that typically frame the planning horizon, depth and breadth of an Architecture Project, and the contents of the EA Repository are Strategy, Portfolio, ___________.
A. Project, and Solution Delivery.
B. Discreet, and Cohesive.
C. Subordinate, and Superior Architecture.
D. Segment, and End-to-end Target Architecture.
Which phase of the ADM has the purpose to develop an Enterprise Architecture Capability?
A. Phase A
B. Phase G
C. Phase B
D. Preliminary Phase
Consider the illustration.
What are the items labelled A, B and C?
A. A-Solution Landscape, B-Architecture Requirements Repository, C-Architecture Landscape
B. A-Architecture Landscape, B-Architecture Requirements Repository, C-Solutions Landscape
C. A-EA Landscape, B-Requirements Repository, C-Artifacts Landscape
D. A-Architecture Requirements Repository, B-Solutions Repository, C-Architecture Landscape
Exhibit:
Consider the illustration. What are the items labelled A, B, and C?
A. A-Enterprise Repository, B-Governance Repository, C-Board Repository
B. A-Architecture Repository, B-Governance Repository, C-Architecture Capability
C. A-Architecture Repository, B-Governing Board, C-Enterprise Capability
D. A-Enterprise Repository, B-Board repository, C-Enterprise Capability
Complete the sentence. When considering agile development, Architecture to Support Portfolio will identify what products the Enterprise needs, the boundary of the products, and what constraints a product owner has; this defines the Enterprise's
A. risk tolerance
B. business continuity
C. backlog
D. operating model
What is present in all phases within the ADM and should be identified, classified and mitigated before starting a transformation effort?
A. Budgetary constraints
B. Risk
C. Schedule constraints
D. Information gaps
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only The Open Group exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your OGEA-103 exam preparations and The Open Group certification application, do not hesitate to visit our Vcedump.com to find your solutions here.