  • Question 111:

    Which role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?

    A. Project Manager

    B. Project Assurance

    C. Senior User

    D. Senior Supplier

  • Question 112:

    Which project management team role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?

    A. Project Manager

    B. Executive

    C. Project Assurance

    D. Quality Assurance

  • Question 113:

    Which role is responsible for briefing corporate or programme management about project progress?

    A. Team Manager

    B. Project Support

    C. Project Board

    D. Project Manager

  • Question 114:

    Are the following statements regarding the Communication Management Strategy true?

    1.

    Defines how and where the project's products will be stored

    2.

    Contains a description of the means and frequency of communication to parties both internal and external to the project

    A. Only 1 is true

    B. Only 2 is true

    C. Both 1 and 2 are true

    D. Both 1 and 2 are false

  • Question 115:

    Which of the following project management team roles can be shared?

    1.

    Project Assurance

    2.

    Executive

    3.

    Senior User

    4.

    Senior Supplier

    A. 1,2,3

    B. 1,3,4

    C. 2,3,4

    D. 1,2,4

  • Question 116:

    Which role is responsible for specifying the benefits and for ensuring that they are subsequently realized?

    A. Project Manager

    B. Project Assurance

    C. Senior User

    D. Executive

  • Question 117:

    Whose responsibility is it to ensure that the project is focused throughout its life on achieving its objectives?

    A. Project Manager

    B. Corporate or programme management

    C. Senior User

    D. Executive

  • Question 118:

    Which of the following management levels sits outside of the project management team?

    A. Directing

    B. Managing

    C. Corporate or programme management

    D. Delivering

  • Question 119:

    Which role is part of the project management team?

    A. Change Authority

    B. Stakeholder

    C. Quality assurance

    D. Corporate or programme management

  • Question 120:

    Which of the following are the three primary stakeholder categories?

    A. User, Supplier and Business

    B. Project, Programme and Corporate

    C. Customer, Executive and Supplier

    D. Business, User and Specialists

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.