  • Question 201:

    Identify the missing words in the following sentence. The Project Board will allocate tolerances [ ? ] to the Project Manager.

    A. for each Work Package

    B. for the project

    C. for each management stage

    D. for each technical stage

  • Question 202:

    Which is a recommended quality review team role?

    A. Project Manager

    B. Presenter

    C. Project Support

    D. Producer

  • Question 203:

    In what product would a product's quality tolerance be defined?

    A. Project Product Description

    B. Product Description

    C. Stage Plan

    D. Quality Management Strategy

  • Question 204:

    When should the Managing a Stage Boundary process be undertaken?

    A. Close to the end of a management stage

    B. After the completion of each management stage

    C. At the end of the final stage

    D. At the end of project start-up

  • Question 205:

    Which is a definition of a risk cause?

    A. The impact of a risk on the stage and project tolerance

    B. The source of a risk

    C. The overall effect of a risk on the Business Case

    D. How likely a risk is to occur in a given project situation

  • Question 206:

    When would the Team Manager be required to produce a Checkpoint Report?

    A. When a Work Package is being negotiated

    B. At the frequency agreed in the Work Package

    C. On completion of the quality-checking activities for each product

    D. When reviewing how a stage is progressing

  • Question 207:

    When is it confirmed if a project's objectives have been achieved?

    A. During the Closing a Project process

    B. During the final end stage assessment

    C. During the Controlling a Stage process

    D. During the Managing Product Delivery process

  • Question 208:

    Which defines the sequence in which the products of a plan should be developed?

    A. Product Description

    B. Product breakdown structure

    C. Project Product Description

    D. Product flow diagram

  • Question 209:

    If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?

    A. Raise an Exception Report

    B. Issue an Exception Plan

    C. Raise an issue

    D. Raise a risk

  • Question 210:

    What process enables an organization to understand the work that needs to be done to deliver a project's products before it is approved?

    A. Directing a Project

    B. Initiating a Project

    C. Starting up a Project

    D. Controlling a Stage

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.