Which of the following are true statements about a Project Brief?
1.
Used to provide a foundation for the Initiating a Project process
2.
Created in the Starting up a Project process
3.
Used by the Project Board to make an assessment of a project's progress
4.
Used as the basis of the Project Initiation Documentation
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Which of the following are typical core activities within configuration management?
1.
Planning
2.
Risk assessment
3.
Verification and audit
4.
Identification
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3 ,4
D. 2, 3, 4
Which is a purpose of the Initiating a Project process?
A. Decide if it is worthwhile to initiate a project
B. Decide on the project approach
C. Establish solid foundations for a project
D. Identify the number of Work Packages required
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
A. Executive
B. Senior User
C. Senior Supplier
D. Project Manager
Identify the missing words in the following sentence.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.
A. Highlight Report
B. Product Status Account
C. Checkpoint Report
D. Work Package
Which is the Change Authority role permitted to authorize?
A. Risks to the project
B. Adjustments to the limits on the change budget
C. Changes to stage tolerance
D. Changes to the project that do not exceed a defined budget
Which is NOT one of the levels of plan recommended by PRINCE2?
A. Benefits Review Plan
B. Project Plan
C. Stage Plan
D. Team Plan
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
A. activities
B. processes
C. products
D. quality
Which is part of quality control?
A. Document the project's acceptance criteria in the Project Product Description
B. Define the quality responsibilities of those involved in the production of the products
C. Produce quality records to show that the planned quality activities have been carried out
D. Maintain the corporate organization's quality management system
Which role is part of the Project Board?
A. Corporate or programme management
B. Risk owner
C. Project Manager
D. Senior Supplier
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.