Which is a purpose of the Plans theme?
A. Identify, assess and control any potential changes to the baseline
B. Establish the project's structure of accountability
C. Assess and control uncertainty
D. Understand whether the targets are achievable
Which of the following is NOT a purpose of the Closing a Project process?
A. Plan the activities required to close a project
B. Enable a comparison of the original objectives of a project against what was actually achieved
C. Enable premature closureif the Project Board request that a project should no longer continue
D. Provide a fixed point at which acceptance for the project product is confirmed
Which statement describes the responsibilities of a risk actionee?
A. Identifying risks to the project that might occur in their department
B. Owning and authorizing the use of the risk budget to fund risk responses
C. Managing, monitoring and controlling of all aspects of an assigned risk
D. Carrying out a risk response action to respond to a particular risk
Which two roles are linked by the Managing Product Delivery process?
A. Corporate or programme management and Project Board
B. Project Board and Project Manager
C. Project Manager and TeamManager D. Team Manager and external supplier
What is the first task of product-based planning?
A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure
Which risk response type is appropriate to respond to an opportunity?
A. Accept
B. Fallback
C. Exploit
D. Transfer
Which principle helps to define what should be included and what should be excluded from a project?
A. Defined roles and responsibilities
B. Focus on products
C. Manage by stages
D. Continued business justification
Which is NOT a type of issue?
A. A problem/concern
B. A constraint
C. An off-specification
D. A request for change
Which should be provided by a project mandate?
A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan
How should the Team Manager report that tolerances are forecast to be exceeded?
A. Create an Exception Report
B. Create a Highlight Report
C. Raise an issue
D. Grant a concession
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.