Which two things should the Scrum Team do during the first Sprint?
(choose the best two answers)
A. Make up a plan for the rest of the project.
B. Define the major product features and a release plan architecture.
C. Analyze, describe, and document the requirements for the subsequent Sprints.
D. Build at least one piece of valuable functionality.
E. Create at least one valuable, useful Increment.
Which two ways of creating Scrum Teams are consistent with Scrum's values?
(choose the best two answers)
A. Bring all the people together and let them organize into Scrum Teams.
B. Managers personally re-assign current subordinates to new teams.
C. Existing teams propose how they would like to go about organizing into the new structure.
D. Managers collaborate to assign individuals to specific teams.
E. The Chief Product Owner determines the new team structures and assignments.
What are three advantages of a Product Owner sharing a clearly defined Product Goal with the Scrum Team?
(choose the best three answers)
A. It helps the Developers estimate the date that the Product Backlog will be complete.
B. It is not mandatory in Scrum. There is no real advantage.
C. It provides a good overall direction so Sprints will feel less like isolated pieces of work.
D. It helps the Scrum Team keep focus and they can weigh any decision against the Product Goal
E. It is easier to inspect incremental progress at the Sprint Review.
Which of the following are true about the Product Owner?
(choose the best two answers)
A. The Product Owner is one person.
B. The Scrum Team can have multiple Product Owners.
C. The Product Owner can be represented by a committee or a team of people.
D. The Product Owner is accountable for ordering the Product Backlog.
How much time must a Product Owner spend with the Developers?
(choose the best answer)
A. Enough so that the Product Owner is confident the Increment will meet the intended value.
B. 40%, or more if the stakeholders agree.
C. As much time as the Developers tell the Product Owner to be present.
D. 100%
What is the timebox for the Sprint Review?
(choose the best answer)
A. 2 hours for a one-month Sprint.
B. 1 day.
C. 4 hours for a one-month Sprint.
D. As long as needed.
True or False: Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.
A. True
B. False
True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.
A. True
B. False
When might a Sprint be cancelled?
(choose the best answer)
A. When the Developers determine the product plan is infeasible.
B. When it becomes clear that not everything will be finished by the end of the Sprint.
C. When the sales department has an important new opportunity.
D. When the Sprint Goal becomes obsolete.
What activities would a Product Owner typically undertake in the period between the end of the current Sprint and the start of the next Sprint?
(choose the best answer)
A. There are no such activities. The next Sprint starts immediately after the current Sprint.
B. Refine the Product Backlog.
C. Update the project plan with stakeholders.
D. Work with the Quality Assurance departments on the Increment of the current Sprint.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSPO-I exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.