Oracle Oracle Certifications 1Z0-466 Questions & Answers

  • Question 91:

    In which process does the Review and Analyze Bid Materials drive the Validated Scope in the Scope Management process?

    A. Financial Management

    B. Infrastructure Management

    C. Organizational Change Management

    D. Bid Transition

  • Question 92:

    Which three risks does Organizational Change Management seek to mitigate?

    A. Employee attrition

    B. Vendor delivery rates

    C. Lack of personal effectiveness

    D. Interruptions to the business

    E. Natural disasters

  • Question 93:

    Select two objectives of the OUM Manage Project Execution and Control phase.

    A. Manage the project resources to deliver on time and in budget.

    B. Gain project acceptance.

    C. Release staff.

    D. Execute against the Project Management Plan.

  • Question 94:

    Which identifies the quality standards that are relevant to the project and how to satisfy them?

    A. Quality Assurance

    B. Quality Control

    C. Quality Planning

    D. Process Improvement

  • Question 95:

    Select two objectives of the OUM Implement Elaboration phase.

    A. Confirm the project scope.

    B. Identify and validate the architecturally significant requirements.

    C. Identify key configuration decisions.

    D. Prepare the system for acceptance test and deployment.

    E. Address critical operational issues.

    F. Obtain acceptance.

  • Question 96:

    Which two statements are true about the Change Control Board (CCB)?

    A. It meets daily during Project Execution and Control.

    B. It is an internal project organization that is responsible for reviewing and resolving change requests.

    C. It is a person, group, or business that has a shared interest in a particular set of activities.

    D. It escalates changes affecting scope to the steering committee.

  • Question 97:

    Select the three constraints that are missing in this Triple Constraint triangle.

    A. Usability

    B. Scope

    C. Cost

    D. Complexity

    E. Product

    F. Schedule

  • Question 98:

    Select the three statements that are true about the Project management Plan.

    A. It is created in the Manage Project Execution and Control phase.

    B. It is the single most important work product produced by the project manager.

    C. Its main focus is on scheduling the project.

    D. It is created by the project manager and the client.

    E. It is a conceptual work product comprised of process components detailing the tools and/or approach for each OUM Manage process.

    F. It provides a framework for the Analysis and Design processes.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-466 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.