You are a Project Manager working on a new project. You have justreceived the Project Scope of documentthat has provided a top-down timelines and budgets for the project. The project has not started.
Which project status is the best choice for this project?
A. Active
B. Inactive
C. What-If
D. Planned
Select the appropriate example that demonstrates how materials are measured inP6.
A. $75/minute
B. $75/Hour
C. $75/linear foot
D. $75/day
You are a Project Manager that used Primavera P6 EPPM Web interface.You are trying to determine ifsome Project level User Defined Fields might be appropriate for one of your projects.YoulaunchPrimavera P6 EPPM Clientto view enterprise data. You areunable to launch theapplication.
What is the probable issue that must be addressed with your System Administrator?
A. You do not have appropriate security privileges.
B. You do not have appropriate license.
C. You are not a Responsible Manager.
D. You need additional memory added to your machine.
Select the statement that best describes a global portfolio.
A. It is available to single users.
B. It is assigned by a filter.
C. It must be manually refreshed.
D. It is available to all users.
E. Access is governed by security.
Select the best definition of Resource within Primavera P6 EPPM.
A. Labor effort required to complete an activity
B. Materials used to complete an activity
C. Anything used to complete an activity
D. Equipment required to complete an activity
Select two true statements regarding Calendars.
A. Global Calendars are available to a subset of projects.
B. Project Calendars are available for the current project only.
C. Only a limited number of calendars can be created.
D. Resource calendars are applied to all Resources with the same Primary Role.
E. Activity type determines whether the activity uses Resource Calendars for scheduling.
F. Activity Calendars are managed by individual Resources.
Select the true statement regarding Global Change.
A. Global change can be executed by any user.
B. Global change can modify Global Codes.
C. Global change can modify Global Security Profiles.
D. Global Change can replace existing project data with new data.
Cost accounts are hierarchical, and .
A. are assigned in Project Details
B. are created and managed at the Project level
C. are applicable to all projects in the EPS
D. are assigned to users with security
You are a Project Manager who ismanaging several projects in Primavera P6 EPPM Web interface.
Identify the valid navigation options for opening a project in the Web interface.
A. In the Personal Workspace/GANTT Chart portlet, double-click the project name.
B. In the Personal Workspace/My Projects, click the project name.
C. In Portfolios/Executive Summary click the project name.
D. In Portfolios/GANTT Chart click the project name.
Identify the true statement.
A. The Must Finish By constraint is used as the starting date for the backward pass.
B. The Must Finish By constraint forces all activities In the project to finish by that date.
C. The Must Finish By constraint affects thetotal Role limits for the project.
D. All activities have negative total float without a Must finish By constraint assigned to the project.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-535 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.