Cost Variance is calculated as .
A. Earned Value Cost - Actual Cost
B. the Actual Cost of Work Performed
C. the Budgeted Cost of Work Scheduled
D. Budget at Completion - Earned Value Cost
Where are "User Defined Fields" typically maintained?
A. in the Web interface, in the preferences section
B. inthe Client interface by the system administrator
C. in the Web interface, on the Activities tab
D. in the Client interface under Admin Preferences
What takes the highest precedence during Resource Leveling?
A. Leveling priority
B. Mandatory constraint
C. Topological sequent
D. Resource Calendar
You are a Project Manager whose projects are integrated with Financial Management System (FMS). TheFMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date.UpdatingPercent complete using the pushed Actual Dates,Actual Costs, and Actual Hours has createdinaccuratepicturesofthe overall%complete, because there are steps withinactivities that clearly have not completed.
Which PercentComplete Typewould be the best selection for activities in this project?
A. Physical
B. Units
C. Effort
D. Duration
Select the true statement regarding Portfolio Scenarios.
A. You can add user access to the Portfolio Scenario from waterline analysis.
B. You can save the Waterline Analysis as a new scenario.
C. You can update individual project status from the Waterline Analysis/Scenario.
D. You can create a new portfolio from the Waterline Analysis.
You are a Portfolio Manager looking for a new portfolio that you manually created for your have clicked the Group By drop-down list in Portfolios. Which option should you select to quickly find your portfolio?
A. Global Portfolio
B. Global Filtered Portfolio
C. User Portfolio
D. User Filtered Portfolio
You are a Portfolio Manager who opened a specific portfolio. Yourefreshed the filter. However, someof the projects that were previously in the portfolio are no longer there. What happened?
A. You no longer have sufficient Project level security to view the "missing" projects' data.
B. Your Web license was revoked to allow other users to interface with the project.
C. The value of the code assigned to the missing projects had changed.
D. The projects were deleted when the Miter was refreshed.
An activity has an Original Duration of 10, and a Remaining Duration of 10.The ActualStartis assignedtothe activity. Physical % is updated to equal 80%. What is the Remaining Duration for this activity?
A. 80
B. 10
C. 2
D. 8
The ProjectManager selects the "Update units when costschange on resource assignments"optionon Calculations tab in Project Details. The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource on an activity. If the User assigns the activity an Actual Cost of $1,000, what is the Actual Units for the resource?
A. 70
B. 40
C. 60
D. 80
Select the true statement regarding Global Preferences in Primavera P6 EPPM Web Interface.
A. Global Preferences are shared among all users.
B. Global Preferences are customized at the user level.
C. Global Preferences are controlled by the System Administrator
D. Global Preferences are controlled by Global Security Profiles.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-535 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.