Your customer has separate organizations to maintain indirect, capital, and billing types of projects. Identify the two setups that can be used to fulfill this requirement. (Choose two.)
A. Project Type
B. Business Unit
C. Project Organization Classification
D. Organization Tree
E. Project Accounting Business Function
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)
A. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
B. The association of a deliverable with a task is dependent on associating a requirement with a task.
C. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
D. You associate a deliverable with a task, independent of associating a requirement with a task.
Your customer wants a team member who is assigned to a project to be able to create and submit a forecast, but not to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)
A. Project Manager
B. Project Administrator
C. Project Application Administrator
D. Project Accountant
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)
A. If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.
B. If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.
C. If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.
D. If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with the lowest number at the lowest level.
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
A. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
B. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
C. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
D. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
E. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
Your customer has a requirement to import and process third-party transactions that are "costed" and "accounted". Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)
A. Import Options
B. Document Options
C. Transaction Source Options
D. Document Entry Options
In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or
created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.
Identify the correct statement about details in the receivables invoice. (Choose the best answer.)
A. The project sends only the invoice header and invoice line description to Receivables, not the invoice distributions.
B. The project sends the invoice header, invoice line description, and the invoice distributions to Receivables.
C. The project sends only the invoice header to Receivables, not the invoice line description and distributions.
D. The project sends the invoice line description and the invoice distributions to Receivables, but not the invoice header.
While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. (Choose two.)
A. You used Create Tree in the action menu.
B. You used Create Tree Version in the action menu.
C. You used View Tree Version in the action menu.
D. You selected the Edit icon for opening the hierarchy.
E. You opened the hierarchy by clicking the name.
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)
A. Accounting date is the same as the original invoice date.
B. Project accounting date is the same as the original invoice date.
C. Project accounting date is the first day of the first open project accounting period.
D. Project accounting date is the last day of the open project accounting period.
E. Accounting date is the first day of the first open accounting period.
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
A. 1000
B. 900
C. 800
D. 600
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-1057-22 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.