  • Question 61:

    When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)

    A. Bulk

    B. Detail

    C. Incremental

    D. Summary

  • Question 62:

    While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)

    A. project classification

    B. project type

    C. project unit

    D. project organization

  • Question 63:

    You have four resources in your organization: P, Q, R, and S.

    Resource P - Project or resource calendar is active.

    Resource Q - Project resource request dates are within the project or resource calendar effective dates.

    Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.

    Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.

    Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)

    A. P

    B. Q

    C. R

    D. S

  • Question 64:

    Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two.)

    A. project

    B. expenditure item

    C. project classification

    D. project plan type

    E. resource

  • Question 65:

    Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)

    A. Expenditure Type

    B. Projects

    C. Contract Line

    D. Contract Header

    E. Task

  • Question 66:

    You are trying to create a custom infolet but are not able to find the "Create Infolet" option in the Infolet repository window. Which two steps should be completed before you can access the "Create Infolet" option?

    A. You must activate Page Composer.

    B. You should be on the Project Custom Objects page.

    C. You must be in an active sandbox.

    D. You should enable the "Create Infolet" option from the Personalize Springboard page.

  • Question 67:

    Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?

    A. Project Budgets

    B. Project Tasks

    C. Project Billing Events

    D. Project Templates

  • Question 68:

    Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)

    A. The application role relevant to the China business unit is not assigned to the project accountant.

    B. The project accountant is not assigned to the external role that grants access to the China business unit.

    C. The US and UK business units are linked to different ledgers than the China business unit.

    D. The China business unit is associated with a different legal entity than the US and UK business units.

  • Question 69:

    What are three configuration items that you need to set up by using the Project Organizations functional area in Project Financial Management configurations? (Choose three.)

    A. Manage Project Unit Organizations

    B. Mange Business Unit

    C. Manage Project Organization Classifications

    D. Mange Project Types

    E. Manage Project Unit Options

  • Question 70:

    You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)

    A. On Hold > Pending Acceptance > Active

    B. On Hold > Pending Approval > Active

    C. Pending Approval > Pending Acceptance > Active

    D. Pending Acceptance > Pending Approval > Active

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-1057-22 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.