You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
A. 1000
B. 900
C. 800
D. 600
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
A. The organization is not classified as a project-owning organization.
B. The organization is not classified as a project expenditure organization.
C. The organization is not included in the organization tree that is assigned to the business unit that owns the PO.
D. The organization is classified as a project unit.
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)
A. Accounting date is the same as the original invoice date.
B. Project accounting date is the same as the original invoice date.
C. Project accounting date is the first day of the first open project accounting period.
D. Project accounting date is the last day of the open project accounting period.
E. Accounting date is the first day of the first open accounting period.
Your customer has a requirement to import and process third-party transactions that are "costed" and "accounted".
Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)
A. Import Options
B. Document Options
C. Transaction Source Options
D. Document Entry Options
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Which three are parameters that are based on which the system identifies the new resources?
A. Department
B. Project Unit
C. Jobs
D. Business Unit
E. Organization
Which component provides a human workflow service that handles all interactions with users or groups in business processes?
A. Security Console
B. SOA Suite
C. Subledger Accounting
D. BPM Worklist
Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)
A. Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule
B. Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate
C. Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule
D. Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule
E. Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two.)
A. project
B. expenditure item
C. project classification
D. project plan type
E. resource
Stigma consulting has been hired by a client to implement Project Management Cloud. Which role should they assign to a user for using the rapid implementation feature to set up the Project Financial Management offering by populating and uploading a Microsoft Excel workbook?
A. Project Executive
B. Project Integration Specialist
C. Project Administrator
D. Project Application Administrator
When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
A. multiple threshold levels
B. single threshold level value
C. single threshold level range
D. multiple threshold level value
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-1057-23 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.