Once the sale of a System z has been made, which of the following individuals is responsible to ensure that the implementation plan is executed?
A. IBM or Business Partner TDA Leader
B. IBM or Business Partner Technical Specialist
C. IBM Installation Planning Representative
D. IBM or Business Partner Client Representative
A System z FTSS needs POWER blades configured for a zBX.
Which of the following procedures should be used for this configuration?
A. The z FTSS configures all components for the zBX using zManager configuration tool
B. The z FTSS should provide the POWER blade requirements to the POWER team
C. POWER team should configure the blade type normally acquired by the customer for a BladeCenter
D. The customer should configure through the IBM Workload Estimator
A customer is migrating to z114 and z/VM V6.1. The existing z9 BC will be used as cold standby system in a separate datacenter. Which of the following is correct?
A. In order to run all guests on the z9 BC both, z9 BC and z114, have to run z/VM V6.1
B. The latest version of z/VM supported on z9 BC is z/VM V5.4. However the guests stay compatible.
C. In order to keep z/VM guests both systems (z114 and z9 BC) need to run z/VM V5.4.
D. The customer has to run z/VM V6.1 as a second level guest on the z9 BC z/VM V5.4The customer has to run z/VM V6.1 as a second level guest on the z9 BC? z/VM V5.4
The System z Technical Specialist is asked by a customer for differentiators of a zBX solution with x86 blades compared to x86 blades in a traditional BladeCenter. Which of the following is a key differentiator?
A. VMware license costs for x86 blades will be the same when integrated into zBX, but management costs will be lower.
B. Software license costs on x86 blades are optimized when integrated into zBX.
C. Unified Resource Manager includes an x86 hypervisor, and management costs are lower.
D. Any existing customer x86 Blades can be integrated into the zBX
Which of the following FICON Express channels is supported on a new build z114 configuration?
A. FICON 2
B. FICON 4
C. FICON
D. FICON 8S
What is the minimum acceptable process or technique to estimate the capacity requirement for a replacement CPC?
A. zCP3000
B. zTPM
C. LSPR capacity table
D. zPCR
A z114 will be defined as a member of an ensemble and use Unified Resource Manger. Which of the following options correctly describe the HMC requirements?
A. a Z114 requires no HMC
B. Requires a primary HMC only
C. Any HMC may be carried forward
D. Both the Primary HMC and Alternate HMC must have various identical components
A System z customer has a new CIO. The CIO is concerned about continuous operations and recovery following a site catastrophe. Which of the following addresses this issue?
A. GDPS
B. DR
C. Parallel Sysplex
D. CBU
A customer is planning to upgrade from a z9 BC to z114. The customer used carry-forward for the FICON cards when purchasing the z9. The FICON cards are used for accessing DASD via a 1Gb SAN. Which of the following is correct?
A. The customer can carry forward the FICON cards to the z114.
B. The customer has to purchase current FICON8S adapters and upgrade the SAN to at least 8Gb.
C. The customer has to purchase current FICON8S adapters and upgrade the SAN to at least 2Gb.
D. The customer has to purchase current FICON8S adapters and upgrade the SAN to at least 4Gb.
A prospective zEnterprise customer is fascinated with the addition of the zBX products. The sales specialist is discussing the flexibility of System z family of servers. Which of the following is a key aspect?
A. Binary compatibility between servers
B. Hot pluggable processor and memory boards
C. Consistent CoD features with entire family
D. Ability to interchange features between systems
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IBM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C4070-604 exam preparations and IBM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.