The System z Technical Specialist is sizing a zEnterprise z196 + zBX for a multi-tier applications, which is running today on z10 EC and distributed environment under AIX. Which of the following should be used for the sizing of the proposed zEnterprise configuration?
A. Use zPCR or zCP3000 for the z196 sizing, and engage a Techline specialist for the POWER7 sizing.
B. Use the MIPS table for z196 sizing and engage a Techline specialist for the POWER7 sizing.
C. Use the COMP Conversion tables for both environments
D. Use zPCR or zCP3000 for the z196 sizing, and use estimated TPM-C ratios for POWER7
A customer will be upgrading their z10 EC to a z196 and would like to position the z196 to take advantage of new PCIe infrastructure for future support. Currently they have two I/O cages. The customer cannot take a future outage to add the new drawer.
Which of the following will position the server for future use of a PCIe I/O drawer?
A. Just perform the upgrade, the existing cards will carry forward into the new PCIe drawer.
B. The drawer can be added later when the customer is ready to order the new PCIe cards.
C. Order the new PCIe OSA-Express4S 1000BaseT and/or FICON Express4S cards now which will drive the new PCIe drawer.
D. The new PCIe drawer cannot be installed concurrently so order the new PCIe OSA-Express4S 10GbE and/or FICON Express8S cards now which will drive the new PCIe drawer.
Which new z196 feature provides significant error detection and correction capabilities for bit, lane, DRAM, DIMM socket and memory channel failures?
A. RAS
B. RAID
C. RACEv
D. RAIM
A new customer has approached a System z Technical Specialist to help them upgrade their older System z mainframe. Growth is minimal. Which of the following is needed to create an initial z114 configuration?
A. Energy consumption
B. Disk Storage Growth Rates
C. Installed Base System Report
D. The number of distributed servers installed
A System z customer is planning to move their data center with several existing System z servers to a new space without a raised floor. Which of the following requirements should the technical specialist discuss with the customer?
A. Ordering the height reduction feature if needed
B. Top Exit Cabling Option is required for all the CPCs
C. Confirm all the System z servers are z9 BC, z10 BC or z114
D. Confirm the new installation is compliant with the Installation Manual for Physical Plugging
A customer technical staff has been briefed on migration to a z114 or z196. They are discussing the new features with the System z Technical Specialist. Which of the following customer statements is incorrect and must be corrected by the Technical Specialist?
A. Addition and removal of z196 I/O cage is disruptive
B. There is Plan Ahead option available for the I/O drawers
C. The I/O drawers can be added or removed non-disruptively
D. The correct mix of I/O cage and drawers is configured based on the number and type of I/O features ordered
During which of the following activities do the customer and the technical specialist define post installation support?
A. During the TDA (Solution Assurance)
B. When establishing the system ship date
C. When configuring the System z using eConfig
D. During the installation of the equipment by the CE
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IBM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C4070-604 exam preparations and IBM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.