What are the various transactions in SAP PS with which a work breakdown structure can be created? There are 3 correct answers to this question.
A. Project planning board
B. Structure planning
C. Create work breakdown structure
D. Project planning
Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer.
A. Cost object
B. Material view
C. Assignments
D. Network
To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element? There are 2 correct answers to this question.
A. Billing element
B. Cost element
C. Account assignment element
D. Pricing element
Which of the following decides whether networks can be header assigned or activity-assigned? There are 2 correct answers to this question.
A. Billing type
B. Network structure
C. Plant
D. Order type
Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element? Please choose the correct answer.
A. Billing plan in project billing elements
B. Manual planning in billing elements in the project structure
C. Hierarchical billing plan
D. Sales order planning
How do you effectively control your project and estimate the POC of WBS elements, activities and activity
elements?
Please choose the correct answer.
A. Progress analysis
B. Project analysis
C. Milestone analysis
D. Activity analysis
Which of the following scenario doesn"t allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released? Please choose the correct answer.
A. The funds commitment in plan indicator is not set
B. The funds commitment in plan indicator is set to value less than 0
C. The funds commitment in plan indicator also has status released
D. The funds commitment in plan indicators is set
You work with Project Builder (CJ20N) and want to use standard templates in your project structure.
Which standard templates can you use?
Please choose the correct answer.
A. Standard cost planning
B. Standard Bill of Material (BOM)
C. Standard time scheduling
D. Standard Milestones
Externally processed activities give rise to planned costs that are equivalent to the prices of the following? There are 2 correct answers to this question.
A. Actual costs
B. Purchasing Info records
C. Price in the activity
D. Services costs
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning? Please choose the correct answer.
A. Customizing key
B. Control key
C. Scheduling key
D. Confirmation key
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.