Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning? Please choose the correct answer. Response:
A. Control key
B. Confirmation key
C. Scheduling key
D. Customizing key
How do you reduce the scheduled duration of internally-processed activities if the time period within which
the activities are to be scheduled is not long enough to process all activities? Please choose the correct
answer.
Response:
A. Reduction
B. Scheduling breech
C. Milestones
D. Capacity breech
Which of the following information regarding cost activity is not relevant for the calculation of planned
costs? Please choose the correct answer.
Response:
A. Control key
B. The cost element is defaulted for cost activities based on the network profile
C. A unit costing that enables detailed planning with multiple cost elements, or an invoicing plan
D. Cost activities based on external services
Which technique is one of the ways to measure the earned value where each milestone corresponds to a
percentage of work completed in an activity or a WBS element in progress analysis? Please choose the
correct answer.
Response:
A. Trend technique
B. Project technique
C. Milestone technique
D. Period indicator technique
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how? Please choose the correct answer. Response:
A. Automatic requirement grouping indictor
B. MRP element indicator
C. MRP groups
D. Material group
Which variant defines the valuation procedure for materials, internal activities, external activities, and
business processes? Please choose the correct answer.
Response:
A. Costing variant
B. Valuation variant
C. Planned cost variant
D. Network variant
Which type of reports allows you to choose the objects whose costs you want to analyze or call up an appropriate list and choose the period you want to evaluate? Please choose the correct answer. Response:
A. Hierarchy reports
B. Cost element reports
C. Period analysis reports
D. Structural reports
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock? There are 2 correct answers to this question. Response:
A. Plant stock
B. Project stock
C. General stock
D. Sales order stock
What is the procurement element for requirements planning?
Please choose the correct answer.
Response:
A. Purchase requisition
B. Purchase order
C. Procurement plan
D. Planned order
Which type of confirmation allows you to confirm various networks, activities, activity elements, and
individual capacities at the same time? Please choose the correct answer.
Response:
A. Open PS interface
B. Collective confirmation
C. Structure information system
D. CATS
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.