In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders
or maintenance orders, for example) to the WBS element that are flagged as account assignment
elements. What is the use of this assignment?
There are 3 correct answers to this question.
Response:
A. This assignment can then be used to display the planned costs of the orders of the project
B. This assignment can then be used to display the unit costs of the orders of the project
C. It can be copied to a new project
D. Cost planning can be moved automatically along with the activities
In which type of project stock G/L account determination for project stock is controlled differently from
collective stock using specific valuation classes for sales order stock and project stock in the material
master? There are 2 correct answers to this question.
Response:
A. Valuated project stock
B. Non-valuate project stock
C. Sales order stock
D. Purchase order stock
Items procured through which of the following methods are not assigned to a stock segment and do not
pass through a warehouse? Please choose the correct answer.
Response:
A. Indirectly
B. Vendors
C. Directly
D. Non project stock items
In which of the following ways Open PS allows you to exchange data directly with MS project? There are 3 correct answers to this question. Response:
A. Create a project in MS project from an SAP PS project
B. Transfer a project from MS project to SAP PS
C. Download MS project and Upload to SAP PS
D. Reconcile data from a project in Microsoft Project with a project in SAP PS
Which manual cost planning method is used in WBS? There are 3 correct answers to this question. Response:
A. Unstructured planning
B. Overall planning
C. Detailed planning
D. Unit costing
What are the different procurement types you can choose between if you choose direct procurement with
item category N?
There are 2 correct answers to this question.
Response:
A. Procurement for network
B. Purchase requisition for network
C. Purchase order for network
D. Third-part order
What do you choose when creating a new network by copying an operative network? There are 3 correct
answers to this question.
Response:
A. PS texts
B. Relationships
C. Milestones
D. WBS elements
In Structure Information System which transactions allow you to analyze and edit the entire hierarchical
structure of a project including documents, PS texts, networks, other orders, investment programs, and SD
documents? There are 2 correct answers to this question.
Response:
A. Network overview
B. Order overview
C. Structure overview
D. Project structure overview
When you assign material components using the BOM transfer function, the system uses the Reference
Point field in the BOM items and activities to establish a logical connection between which items? There
are 2 correct answers to this question.
Response:
A. Individual BOM items
B. Multiple BOM items
C. Multi level BOM
D. Network activities
How do you optimize cash flows to maximize project profits and reduce project costs? Please choose the
correct answer.
Response:
A. PS Cash management
B. Mile stone billing
C. Milestone management
D. Billing plan
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.