Which of the following cannot be entered when using service activities in networks for planned and
unplanned services?
Please choose the correct answer.
Response:
A. Goods receipt
B. Goods issue
C. Service entry
D. Service acceptance
Consider a scenario where you have started by displaying the planned costs for the entire project and how these planned costs are distributed among the various value categories for WBS element WBS 2. You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods. Which type of reporting allows you to achieve this?
Please choose the correct answer. Response:
A. Commercial project reports
B. Cost element reports
C. Planned cost reports
D. WBS reports
Which type of down-payment chain allows you to monitor receivables to customers and to gain information
on past and future incoming payments? Please choose the correct answer.
Response:
A. Credit-side down payment
B. Debit-side down payment
C. Credit memo
D. Debit memo
When using budgeting and active availability control, which business transactions affect the current
budget? There are 3 correct answers to this question.
Response:
A. Cost element planning
B. Original budget
C. Revenues
D. Transfers
E. Supplements
Which business functions from the following are supported by network activities? There are 3 correct
answers to this question.
Response:
A. Billing plans
B. Internal activity
C. External activity
D. Periodic processing
Which of the following can be derived automatically when you carry out scheduling in projects with
networks? There are 2 correct answers to this question.
Response:
A. Activity dates
B. WBS element dates
C. Network dates
D. Scheduling dates
The determination of the settlement profile and result analysis key is based on WBS-operative indicators
for which of the following? There are 2 correct answers to this question.
Response:
A. Billing element
B. Settlement rule
C. Operative rule
D. Account assignment
Response:
A. The revenue value of the sales order item can be assigned to dates in the billing plan.
B. The amount to be billed is entered directly in the milestones of the WBS elements or activities.
C. The billing block on a billing date is removed when the related milestone is confirmed with an actual date.
D. For each billing date in a billing plan, you can define whether the date is fixed or whether it is moved along with the dates of the milestone.
E. If a milestone is to be used as a date in a billing plan, the "Sales document date" indicator must be activated in the milestone.
Project System has its own Organizational structure, which can be a matrix structure.
Please choose the correct answer.
Response:
A. True
B. False
Which account assignment category is important for non-valuated project stock with WBS and sales order
item?
Please choose the correct answer.
Response:
A. E = quantities and values managed in the sales order item
B. D = quantities managed using sales order item and values managed in projects
C. G = plant stock, values managed using projects
D. Q = quantities and values managed in projects
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM22_64 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.