Which of the following is NOT an event-driven control?
A. Project mandate
B. Checkpoint Report
C. Exception Report
D. End of a stage
Which is a responsibility of a risk owner?
A. Identify risks to the project that might occur in their department
B. Own and authorize the use of the risk budget to fund risk responses
C. Manage, monitor and control all aspects of an assigned risk
D. Determine project risk appetite
Which is a type of issue?
A. An expected dis-benefit
B. An off-specification
C. A project outcome
D. A scope tolerance
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
A. Controlling a Stage
B. Closing a Project
C. Directing a Project
D. Managing a Stage Boundary
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
A. minimum necessary is done to decide if a project is worthwhile
B. aim is to establish sound foundations to achieve a successful project
C. Project Brief is assembled and approved
D. project approach appropriate for delivering a project is selected
Which of the following is NOT a purpose of the Closing a Project process?
A. Plan the activities required to close a project
B. Enable a comparison of the original objectives of a project against what was actually achieved
C. Enable premature closure if the Project Board request that a project should no longer continue
D. Provide a fixed point at which acceptance for the project product is confirmed
Which is NOT a purpose of the Organization theme?
A. Define a project management team structure
B. Define the level of tolerance for each level of the project management team
C. Define the Project Board's responsibility for directing the project
D. Define which role is accountable for the project's success
Which of the following statements about the Closing a Project process are true?
1.The Closing a Project process provides a fixed point for the receipt of completed Work
2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Which product identifies the management stages and timescales of a project?
A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan
How should the Team Manager report that tolerances are forecast to be exceeded?
A. Create an Exception Report
B. Create a Highlight Report
C. Raise an issue
D. Grant a concession
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.