Exam Details

  • Exam Code
    :EX0-002
  • Exam Name
    :PRINCE2 FoundationExam
  • Certification
    :Exin Certification
  • Vendor
    :EXIN
  • Total Questions
    :149 Q&As
  • Last Updated
    :Mar 31, 2025

EXIN Exin Certification EX0-002 Questions & Answers

  • Question 121:

    Which is part of the PRINCE2 definition of a project?

    A. An undertaking that consists of at least two management stages

    B. A description of what must be delivered in order to gain acceptance

    C. The total of a plan's products

    D. A temporary organization that is created for the purpose of delivering business products

  • Question 122:

    Which is a type of issue?

    A. A lesson

    B. A request for change

    C. An Exception Report

    D. A risk with an estimated high impact

  • Question 123:

    Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope.

    A. benefits, progress, risk,

    B. benefits, quality, risk,

    C. change, quality, progress,

    D. benefits, customers, quality,

  • Question 124:

    Which task is performed by the Change Authority?

    A. Set a change budget

    B. Approve or reject a request for change within approved limits

    C. Refer changes that exceed budgetary limits to the Project Manager for approval

    D. Update the configuration management system when a change is approved

  • Question 125:

    Identify the missing word in the following sentence, A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.

    A. costs

    B. risks

    C. benefits

    D. issues

  • Question 126:

    Which process provides the Project Board with the information it requires in order to commit resources to the project?

    A. Managing Product Delivery

    B. Initiating a Project

    C. Controlling a Stage

    D. Directing a Project

  • Question 127:

    Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

    A. Principles

    B. Processes

    C. Tailoring PRINCE2 to the project environment

    D. Themes

  • Question 128:

    Which should be funded by a change budget?

    A. Increase in agreed scope

    B. Initiation stage

    C. Change Authority

    D. Handover activities

  • Question 129:

    Which of the following describes a use of a Configuration Item Record?

    A. Define the identification scheme to be applied to the project

    B. Identify the techniques and procedures required within the Work Package

    C. Record the change in a product's status

    D. Record the reporting requirements for the Work Package

  • Question 130:

    Which characteristic distinguishes a project from regular business operations?

    A. Produces benefits

    B. Introduces business change

    C. Manages stakeholders

    D. Incurs cost

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.