When should a performance baseline be captured?
A. after the initial installation of the equipment, during normal daily operation
B. after the initial installation of the equipment, during peak operating conditions
C. before and after each step of the initial installation of the equipment
D. three times a day during the first week following the initial installation of the equipment
Which HP Insight Diagnostics log displays POST errors?
A. Test Log
B. Error Log
C. Integrated Management Log (IML)
D. Sys Log
How does a c7000 enclosure retain air handling integrity when a server blade is removed?
A. The enclosure design uses blank panels to prevent air loss.
B. A blanking panel causes the air flow to reverse, allowing warmer air to escape.
C. The enclosure uses a self-closing door to prevent air loss.
D. The fans increase in revolutions per minute to increase air volume.
Which feature of the BL465c G7 allows the server to accommodate 16 DIMM slots and retain the half- height form factor?
A. PCIe Gen 2 x8 mezzanine expansion slots
B. AMD SR5690/SP5100 chipset
C. Hot Plug Drive Drawer
D. Smart Array P410i Controller with 1GB FBWC
Which interconnect can be used with the Fibre Channel over Ethernet (FCoE) capability of the new G7 Series of c-Class blades?
A. HP 1/10Gb-F Virtual Connect Ethernet
B. HP Virtual Connect Flex-10 10Gb Ethernet
C. Virtual Connect FlexFabric
D. HP ProCurve 6120G/XG interconnect
E. HP Virtual Connect FC Module
What happens when you turn the enclosure UID to "On" on the Insight Display of a c7000 enclosure?
A. The rear enclosure UID LED illuminates and the color of the Insight Display changes to blue.
B. The front enclosure UID LED illuminates and the color of the Insight Display changes to blue.
C. The rear enclosure UID LED illuminates and the color of the Insight Display changes to green.
D. The front enclosure UID LED illuminates and the color of the Insight Display changes to green.
Which full-height device bays are in Zone 3 of a c7000 enclosure?
A. 1 and 2
B. 3 and 4
C. 5 and 6
D. 7 and 8
Which HP BladeSystem component is used for power allocation and control for all blades and interconnects?
A. Rack and Power Manager
B. Power Manager
C. Onboard Administrator
D. Insight Display
What is the maximum number of c3000 enclosures that can be installed in a 42U rack?
A. 4
B. 5
C. 6
D. 7
Which HP c-Class server blades take up two c3000 enclosure server bays? (Select two.)
A. BL860c
B. BL870c
C. BL685 G7
D. BL490 G6
E. BL2x220c G6
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only HP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your HP2-T26 exam preparations and HP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.