All of the following are part of the monitoring and controlling process group EXCEPT:
A. updating the project charter.
B. updating the project management plan.
C. implementing change requests.
D. updating the project scope.
Which of the following techniques can a project manager use to assist with quality planning? (Select Three).
A. Peer review
B. Critical Chain Method (CCM)
C. Inspection
D. Performance Evaluation and Review Technique (PERT)
E. Work Breakdown Structure (WBS)
F. Benchmarking
Which of the following would be goals of an effective kick-off meeting? (Select Two).
A. To create the project charter
B. To create the statement of work (SOW)
C. To outline the communication plan
D. To set team member expectations
E. To determine the critical path of the project
A project manager receives formal leadership authority from which of the following documents?
A. Resource matrix
B. Project charter
C. Work Breakdown Structure (WBS)
D. Statement of Work (SOW)
Which of the following quality option costs BEST identifies the expense of inspecting deliverables to prevent flawed products from reaching the customer?
A. Actual costs
B. Failure costs
C. Appraisal costs
D. Contract costs
A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?
A. Reviewing holiday and vacation schedule with all team members.
B. Getting the email address of all the employees.
C. Locating each employee on the map in the office.
D. Understanding the international country code of all the team members.
The project team is recognized for contribution efforts and is officially released from the project during which of the following stages?
A. Formal acceptance
B. Administrative closure
C. Lessons learned
D. Transition plan
Which of the following would measure a project's validity?
A. Risk analysis
B. Strategic alignment
C. Resource allocation
D. Gantt chart
The purpose of a WBS dictionary is to provide:
A. additional details for each component of the WBS, and for each component provide a brief definition of its statement of work, outputs, actual activities and pertinent milestones.
B. a detailed glossary of terms used in the WBS.
C. written authorization to sanction work on a particular work-package within the WBS, and define the methods for its implementation and the monitoring of its performance.
D. a hierarchical decomposition of the work to be undertaken to address the objectives and meet the requirements of the project at the lowest level.
The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?
A. Closing
B. Planning
C. Executing
D. Monitoring/Controlling
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.