  • Question 91:

    Which of the following represents a lead that is done in response to project compression?

    A. Delaying

    B. Crashing

    C. Overtime

    D. Fast tracking

  • Question 92:

    Which of the following describes the purpose of a war room on a project?

    A. It is a space where project managers negotiate for project team resources

    B. It is a wireless access room which allows for strong Internet connectivity

    C. It is a location set aside for project use

    D. It is a room used to send conflicting team members to work out conflicts

  • Question 93:

    Which of the following represents a good reason for formally closing out a project?

    A. To provide historical information for future projects

    B. To manage stakeholders' expectations

    C. To promote team cohesiveness

    D. To keep a record in case someone comes back later with an issue after transition

  • Question 94:

    Which of the following describes an assumption?

    A. Not used on projects, because certainty is needed to proceed with planning

    B. An unqualified estimate that can be firmed up later

    C. Treated as true for the purpose of planning

    D. A limitation that can impact the project that must be considered

  • Question 95:

    Which of the following is an input into developing the project charter?

    A. Business case

    B. Project scope statement

    C. Requirements documentation

    D. Project schedule

  • Question 96:

    Which of the following would aid in the creation of a communication distribution plan?

    A. Risk register

    B. Stakeholder register

    C. Issue log

    D. Change control log

  • Question 97:

    Which of the following shows how often contracts would be closed for the procurements on a project?

    A. During phase gate review

    B. After the project is completed

    C. At the end of the project

    D. At the end of the contract

  • Question 98:

    Which of the following is the budget amount needed to finish a project?

    A. ETC

    B. VAC

    C. EAC

    D. BAC

  • Question 99:

    Which of the following can aid in the identification of root causes of defects?

    A. Run charts

    B. Ishikawa diagrams

    C. Histograms

    D. Pareto charts

  • Question 100:

    Which of the following can aid in the identification of trends?

    A. Pareto charts

    B. Ishikawa diagrams

    C. Histograms

    D. Run charts

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.