  • Question 301:

    Which of the following should be used when determining the details of a project component or scope entry?

    A. WBS Dictionary

    B. Project Management Plan

    C. Work Breakdown Structure

    D. Project Charter

  • Question 302:

    A project's deliverable has been assigned to a team located in a different country. Although it is understood that daily reports are due by close of business every weekday, the external team's reports are consistently being delivered after business hours. Which of the following is MOST likely occurring?

    A. The external project team did not understand the report requirements due to the language barrier.

    B. External project team members are always allowed to deliver reports late.

    C. The project manager has not taken into consideration the time zone difference.

    D. Cultural differences between the project manager and the external team were not considered.

  • Question 303:

    The project manager wants to report to the stakeholders to date project's cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, which of the following is the cost variance?

    A. -5%

    B. 5%

    C. -$10,000

    D. $10,000

  • Question 304:

    Some of the stakeholders are losing interest in the project because of its length. Which of the following should the project manager implement in this situation?

    A. Remove the stakeholders who are losing interest to ensure successful completion of the project.

    B. Limit communication with the stakeholders to the bare minimum and only report on the progress and not the issues.

    C. Implement a concise and reoccurring communication plan which focuses on the project goal and accomplishments.

    D. Review the project goal with the stakeholder and allow them to make the appropriate changes to keep them interested.

  • Question 305:

    The project manager is reviewing the Pareto chart to identify if the life cycle of a deliverable is producing software bugs. Which of the following are represented in the chart? (Select TWO).

    A. Number of work units affected by the bug

    B. Percentage of bug types occurring

    C. Software bug counts

    D. Root cause of bug occurrence

    E. Affect of the bug occurrence

  • Question 306:

    Which of the following is the project manager implementing when they allocate additional resources to a set of tasks that are in the critical path and are slowing down the project completion?

    A. Crashing

    B. Optimizing

    C. Controlling

    D. Fast tracking

  • Question 307:

    Additional company employees have been assigned to the project. Which of the following will be affected?

    A. The timeline may be positively affected at the expense of the project cost.

    B. This change does not affect the triple constraint because the additional employees are already on the company payroll.

    C. The quality of the product will improve but it will add more time to the project to train the new employees.

    D. Total project cost will be reduced because the project can now be completed sooner.

  • Question 308:

    A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed. Which of the following should be done NEXT?

    A. Implement the change

    B. Update the change registry

    C. Document the change

    D. Perform an impact analysis

  • Question 309:

    While performing a scheduled walkthrough at a construction site, the customer points out a discrepancy. Which of the following is the FIRST step that should be taken before submitting a change control form?

    A. Consult the project sponsor

    B. Identify the change

    C. Perform a feasibility study

    D. Perform impact analysis

  • Question 310:

    A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the following is TRUE about this scenario?

    A. The new piece of software will most likely expand the scope of the project therefore a new scope statement must be written.

    B. The current project must be completed and a new project can be started to implement the additional software.

    C. Quality management metrics are affected therefore the project manager should review the quality of the project.

    D. Project schedule may be affected and the project manager must follow the change control process.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.