Which of the following bodies has external influence regarding standards compliance?
A. PMO
B. OBS
C. ISO
D. CCB
Which of the following conflict resolution techniques results in mutual agreement among conflicting parties?
A. Forcing
B. Avoiding
C. Smoothing
D. Compromise
Which of the following conflict resolution techniques emphasizes agreeable points in order to move the project forward?
A. Avoiding
B. Confronting
C. Smoothing
D. Forcing
A project team is meeting monthly for their project risk review. During the brainstorm, one of the team members mentions that a risk to the project could be a delay with the servers. Which of the following is the BEST response?
A. Exploit
B. Enhance
C. Avoid
D. Share
A project team is about to deliver on a two year long project when they are informed of new Government laws that directly affect the product. The team meets with their stakeholders to discuss the impact to the project and determine that additional laws need to be taken into account before go-live. The NEXT step the project manager needs to take is:
A. Re-direct the development team.
B. Create a change request.
C. Update the issues log.
D. Hold a meeting with the users.
A project risk is defined as a condition or event that:
A. might occur and needs monitoring.
B. cannot be avoided.
C. does not directly affect the project.
D. occurs and needs mitigating.
After a project team has almost completed the development on the project's original requirements, the users identify functionality that is necessary but was not in the original requirements. The project manager MUST:
A. Update the risk register.
B. Implement the change.
C. Cancel the project.
D. Generate a change request.
When creating a communication plan, the project manager should include the escalation path, format and frequency of meetings, and:
A. Roles and responsibilities
B. Risk and issue log
C. Budget
D. Scope
A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?
A. Change request
B. Risk
C. Resource constraint
D. Scope creep
A network diagram is used to organize which of the following?
A. Critical path
B. Defects
C. WBS
D. Issues
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.