During which of the following process groups is the project charter developed?
A. Pre-project setup
B. Project execution
C. Project planning
D. Project control
A project manager needs to determine how much it will cost for a third party to complete certain deliverables and the steps they will take to complete those deliverables. Which of the following should the project manager do to gather this information?
A. Issue an RFQ
B. Issue an RFP
C. Create a WBS
D. Develop a SOW
The key stakeholder requires the project manager to advance the completion date before funding runs out. The project manager has had problems with this stakeholder in the past and wants to document this request. Which of the following should the project manager do? (Select TWO).
A. Complete a project change request form.
B. Analyze the project impact.
C. Update the project scope statement.
D. Revise the scope management plan.
E. Monitor the work performance.
Exploiting is considered to be a response of which of the following?
A. Risk opportunity
B. Conflict resolution technique
C. Risk threat
D. Resource leveling technique
Which of the following documents would include product warranty information?
A. Transition plan
B. Quality management plan
C. Procurement plan
D. Project charter
Which of the following would be found in a transition plan? (Select TWO).
A. Key milestones
B. Project acceptance criteria
C. Training requirements
D. Tollgate approvals
E. Extended support
A project scope document would include which of the following? (Select TWO).
A. WBS
B. Key performance indicators
C. Assumptions
D. Risk matrix
E. Network diagram
Which of the following would be found in a post-mortem analysis? (Select TWO).
A. Lessons Learned
B. Transition Plan
C. Project sponsor signoff
D. Maintenance responsibilities
E. Reasons for early termination of the project
Which of the following is required to validate a project?
A. Problem statement
B. Signed project charter
C. Key project deliverables
D. Alignment with the organization's strategic goals
Which of the following is an advantage of using GERT?
A. Discretionary dependencies can be used
B. Allows using dummy activities
C. Slack time is more easily shown
D. Multiple outcome options can be shown
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.