A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.
What should the program manager do next?
A. Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.
B. Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board.
C. Recommend that the component project manager complete work activity to deliver benefits to the organization.
D. Update the benefits management plan to reflect the impact of the change on the program and its intended benefits.
The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee. What do the current findings show?
A. Project C is running behind schedule and is over budget; projects A, B, and D are on schedule.
B. Project A is running ahead of schedule and is under budget; projects B, C, and D are behind schedule.
C. The overall program is performing within an acceptable level of variance.
D. Project A is running behind schedule and is over budget; projects B, C, and D are on schedule.
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million. Since the shutdown was not anticipated, what should the program manager do first?
A. Implement the appropriate risk response plan and inform the stakeholders of the planned actions.
B. Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.
C. Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.
D. Collaborate with the sponsor to determine options and negotiate a new date for the milestone.
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?
A. Certify contract completion
B. Conduct a procurement audit to review the procurement process
C. Assess all contracts to ensure all agreed conditions are met
D. Review contract management plan for completeness
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline. What key elements should be included in the benefits register to achieve this goal?
A. Plans for tracking and communicating risks associated with the program
B. Plans for conducting program quality assurance and control on a regular basis
C. Plans for program schedule control to meet the shorter timeline
D. Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits.
A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.
What should the program manager do next?
A. Reassess the project manager's credentials
B. Assign a different project manager
C. Review the skill requirements of the project
D. Apply the competence assessment techniques to resolve the issue
A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager's next step?
A. Assign project managers and resources
B. Classify the program's benefits
C. Identify the program sponsor and program stakeholders
D. Develop the program business case
The program manager defines the program objectives, requirements, and develops a high-level road map.
To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?
A. Program governance board
B. Program management office
C. Change control board
D. Project managers on the program
A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?
A. Key performance indicators
B. Benefits management plan
C. Communications management plan
D. Ishikawa diagram
An aircraft manufacturer is engaged by an airline to build a fleet of new airliners. The program charter has been approved, but the stakeholders are concerned that the delivery method of the program may not meet their expectations.
Using the program master schedule, what will the program manager incorporate to align the program with the expectations of the stakeholders?
A. Program work breakdown structure (PWBS), program scope statement, and benefits management plan
B. PWBS, benefits management plan, and program financial management plan
C. Program charter, PWBS, and program scope statement
D. Program scope statement, benefits management plan, and program financial management plan
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PGMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.