How do you define operations for preventive maintenance tasks? Please choose the correct answer. Response:
A. By assigning the operations directly to the maintenance plan
B. By assigning the operations directly to the maintenance item
C. By assigning the task list to the maintenance plan
D. By assigning the task list to the maintenance item
What is a method for loading data from source system datasets to a Data Source extraction structure?
Please choose the correct answer.
Response:
A. Extractor
B. Transfer structure
C. Info provider
D. Info source SAPC TPI.lV|3O 67E>
To display overhead costs in a maintenance order, you need to assign a costing sheet in Customizing.
To which parameter do you assign the costing sheet?
Please choose the correct answer.
Response:
A. Version for cost estimates
B. Costing type
C. Valuation categories
D. Valuation variant
Response:
A. Define shutdown
B. Cross-department execution
C. Procuring external services
D. Procuring external material
E. Ensures empIoyee's security
Data on measuring point contain the following. Please choose the correct answer. Response:
A. Stock
B. Material
C. Measurement position
D. Operations
What all are the 2 inputs of structure indicators There are 2 correct answers to this question Response:
A. The edit screen
B. The hierarchy levels
C. Middle levels
D. Bottom levels
E. Upper levels
Your customer wants to assign maintenance orders to network actMties automatically with the
Maintenance Event Builder (MEB).
Which of the following steps must you perform?
There are 2 correct answers to this question.
Response:
A. Set the define Transfer of Project or Invest Program indicator.
B. Assign maintenance orders manually to a revision with revision type WPS-controlled.
C. Assign a network to a revision with revision type WPS-controlled.
D. Assign a hierarchical task list to a notification.
E. Assign the Reference PM/PS element to task list headers and network actMties.
What are the general settings of maintenance notification? There are 3 correct answers to this question. Response:
A. Field selection
B. List editor
C. Condition indicator
D. Managerial values
E. Catalog
Your customer wants to view a list of all planned materials in multiple maintenance orders with order status
CRTD. Which of the following standard reports can you use to find the information required? There are 3
correct answers to this question.
Response:
A. The order and operation list
B. The material availability report
C. The operation list
D. The materials where-used report
E. The order list
What all are the steps take part in external work center. There are 2 correct answers to this question. Response:
A. Technical completion
B. Notify
C. Process
D. Order
E. Structure
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TPLM30_67 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.