You want to determine which operations of the routing should be considered in a product cost calculation. How do you do this? Note: There are 2 correct answers to this question.
A. By marking the cost indicator in the control key assigned to the operation
B. By marking the Relevance to Costing indicator in the operation
C. By assigning a cost center to the work center in the operation
D. By defining a usage key in the header of the routing.
You create alternative CO versions for your controlling area, in addition to version 0. What would you use additional CO versions for? Note: There are 2 correct answers to this question.
A. To store data of alternative plan costing runs
B. To store different plan data
C. To store data of parallel valuation
D. To store different budget data
In a standard system delivery, how many free characteristics can be added to an operating concern?
A. 0-70
B. 101-150
C. 71-100
D. Over 150
You want to run an assessment cycle in Profitability Analysis to allocate cost center costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?
A. Cycle iteration
B. Tracing factor
C. Sender cost objects
D. Template
In the material master record there are three planned prices: ""Planned price 1"", ""Planned price 2""and""Planned price 3"". What do you use them for?
A. To valuate goods movement
B. To valuate the materials in cost estimates
C. To valuate material stocks
D. To update the standard price during the release of a standard cost estimate
To which object can you settle an internal order using cost elements with cost element category 21 (internal settlement)? Note: There are 3 correct answers to this question.
A. Sales order item
B. WBS element
C. General ledger account
D. Network
E. Asset
What can you do with statistical internal orders?
A. Apply overhead rates to the internal order.
B. Settle costs to a cost center.
C. Simultaneously post to a cost center.
D. Transfer posting to another internal order.
What are some of the unique attributes of an assessment cycle in Controlling? Note: There are 2 correct answers to this question.
A. They use a secondary cost element during transfer.
B. They transfer only primary costs.
C. They transfer primary and secondary costs.
D. They use the original cost element during transfer
In the Product Cost by Order process, what does the system calculate depending on the order status?
A. Both WIP and variances
B. WIP at actual costs or variances
C. WIP at target costs or variances
D. WIP at percentage of completion (PoC) method or variances
You have implemented Product Cost by Sales Oder in conjunction with cost-based POC results analysis in your organization.
Plan revenue = 3000; Plan costs = 2000 Actual revenue = 1200; Actual cost=1000
What data does the system calculate during results analysis?
A. "Revenue = 1500; Cost of sales = 1000; Revenue surplus =300"
B. "Revenue = 1200; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 200"
C. "Revenue = 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 300"
D. "Revenue = 1200; Cost of sales = 1000; Revenue surplus =200"
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS4CO_2020 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.