  • Question 81:

    For a Kanban to be successful which of these must occur?

    A. Consistent cycle times

    B. Fairly stable process demand of product or service

    C. Low defect rate of incoming product or service

    D. All of the above

  • Question 82:

    SPC Charts are used extensively in different business and decision-making environments. In this example a vendor is being selected based on speed of delivery. Which of the conclusions would help you pick a vendor for your needs regarding lead-time of delivery from your vendors? (Note: There are 4 correct answers).

    A. Vendor A with a much shorter lead time in delivery

    B. Vendor B as it has a better consistency (lower variance) on lead time

    C. Vendor B since Vendor A shows a situation out of control as shown in red

    D. Vendor B since the Control Limits are much narrower than Vendor A

    E. Vendor B has higher lead time, but a process with much narrower Control Limits

  • Question 83:

    Which of these items are not part of what is necessary for successful Kaizens?

    A. Good lighting

    B. Management support

    C. Operator support

    D. Analysis tools

  • Question 84:

    When a Belt implements an improvement that is automated thus requiring no particular understanding for use he has applied which Lean tool?

    A. Mistake Proofing

    B. Kaizen Event

    C. 5S

    D. None of the above

  • Question 85:

    Kanban establishes a means of monitoring production, conveyance and delivery information such that efficient flow is established. The method used by Kanban is to require a _________ before anything moves.

    A. Sign-off

    B. Signal

    C. Bell to ring

    D. Work order

  • Question 86:

    Kaizens or Kaikakus and Six Sigma projects are intended to create breakthrough, significant process improvement versus minor, incremental improvements.

    A. True

    B. False

  • Question 87:

    Using this partial Z Table, how many units from a month's production run are expected to not satisfy customer requirements for the following process? Upper specification limit: 7.2 Lower specification limit:

    4.3 Mean of the process: 5.9 Standard Deviation: 0.65 Monthly production: 450 units

    A. 3

    B. 7

    C. 10

    D. 12

  • Question 88:

    If a Six Sigma project was to reduce changeover times and the team found the project success was decreasing over time since changeover times began to creep back up, which Lean tools should be considered in the Control Phase to reestablish and sustain the project success?

    A. Improve the lighting to assure adequate visibility

    B. Confirm a Visual Factory exists to assure proper communication of status of machines

    C. Implement Kanbans to assure enough inventory for the process step

    D. Reword the standardized work instructions to use active verbs and not passive phrases

  • Question 89:

    A. Are setups optimized for lower scrap levels?

    B. Can extra inventory be seen easily?

    C. Can changeover challenges be recognized?

    D. Are unneeded tools or supplies easily noted?

  • Question 90:

    Situations where standardized work needs to be incorporated include all of these except _____________________.

    A. Changeover instructions incomplete

    B. Lack of a system to assure proper inventory levels at repair stations

    C. Machines continually operating to reduce the labor cost per piece

    D. Process flow for the same product assembly taking various cycle time for completion

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Six Sigma exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your LSSMBB exam preparations and Six Sigma certification application, do not hesitate to visit our Vcedump.com to find your solutions here.