  • Question 91:

    User and Supplier are two of the three primary stakeholder interests that must be represented on the Project Board at all times. What is the third interest?

    A. Customer

    B. Business

    C. Programme

    D. Corporate

  • Question 92:

    Which of the following management levels sits outside the project management team, but will be responsible for commissioning a project?

    A. Directing

    B. Managing

    C. Corporate or programme management

    D. Delivering

  • Question 93:

    Which role organizes and chairs any Project Board reviews?

    A. Project Manager

    B. Executive

    C. Team Manager in the current stage

    D. Member of Project Support with administrative skills

  • Question 94:

    Which role is responsible for ensuring that the expected benefits are realized?

    A. Project Manager

    B. Project Assurance

    C. Senior User

    D. Executive

  • Question 95:

    Whose responsibility is it to assure the project's stakeholders that the project remains desirable, viable and achievable at all times?

    A. Project Manager

    B. Corporate or programme management

    C. Senior User

    D. Executive

  • Question 96:

    Which role is the single focus for day-to-day management of the project?

    A. Project Manager

    B. Executive

    C. Project Support

    D. Team Manager

  • Question 97:

    Select the missing words from the following sentence... The Senior User is responsible for ensuring that the project produces products which will deliver the desired [ ? ].

    A. Outcomes

    B. Benefits

    C. Outputs

    D. Changes

  • Question 98:

    Identify the missing word in the following sentence... A Project Board member is responsible for [?] Assurance

    A. Product

    B. Risk

    C. Quality

    D. User

  • Question 99:

    Which process ensures that plans for realizing the post-project benefits are managed and reviewed?

    A. Closing a Project

    B. Initiating a Project

    C. Directing a Project

    D. Starting up a Project

  • Question 100:

    Which process can trigger a premature close of the project?

    A. Directing a Project

    B. Controlling a Stage

    C. Managing a Stage Boundary

    D. Closing a Project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.