  • Question 1101:

    What is the purpose of a change budget?

    A. To correct any errors found in products produced by suppliers

    B. To pay for any increase in scope

    C. To implement risk actions, such as fallback plans

    D. To supplement any cost tolerance being exceeded

  • Question 1102:

    Which of the following is FALSE regarding the Change theme?

    A. Change control should be used to prevent changes being made to baselined products

    B. Issues can affect the project's performance targets of time, cost, quality, scope, benefits and risk

    C. A pre-requisite of effective issue and change control would be an appropriate configuration management system

    D. Without issue and change control being applied, a project will become unresponsive to its stakeholders

  • Question 1103:

    Who are allowed to raise an issue?

    A. Only the Project Manager and Team Manager

    B. Anyone with an interest in the project or its outcome

    C. Only the Change Authority

    D. Only members of the project management team

  • Question 1104:

    Which product would be updated to show that a decision has been made on an off-specification which has now been closed?

    A. Quality Register

    B. Daily Log

    C. Issue Report

    D. Risk Register

  • Question 1105:

    If a product's weight was specified to be 300 grams but could only be built to a weight of 400 grams, which of the following would be created?

    A. Exception Plan

    B. Request for change

    C. Off-specification

    D. Exception Report

  • Question 1106:

    What is a purpose of the Change theme?

    A. Prevent change to anything agreed in the Project Initiation Documentation

    B. Ensure any potential changes to baselined products are controlled

    C. Ensure that the correct versions are delivered to the customer

    D. Assess changes to only the specialist products

  • Question 1107:

    Which product confirms the version numbers of all products being developed within a given stage?

    A. Configuration Item Record

    B. Stage Plan

    C. Work Package

    D. Product Status Account

  • Question 1108:

    Identify the missing word from the following sentence... PRINCE2 uses the term [ ? ] to cover any relevant event that has happened, was not planned, and requires management action?

    A. Risk

    B. Change

    C. Issue

    D. Exception

  • Question 1109:

    According to PRINCE2, as well as holding informal problems/concerns, which product can also be used to record required actions or significant events not caught elsewhere?

    A. Daily Log

    B. Risk Register

    C. Issue Register

    D. Project notebook

  • Question 1110:

    Which option describes something that should be provided by the project, but currently is not (or is forecast not to be) provided?

    A. Problem/concern

    B. Concession

    C. Off-specification

    D. Exception Report

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.