In which product are acceptance criteria documented?
A. Project Product Description
B. Product Description
C. Quality Register
D. Quality Management Strategy
If a team member had a suggestion to improve a product, how would they do this?
A. Raise the suggestion as an issue
B. Add the details of the suggested improvement to the Quality Register
C. Add the details of the suggestion to the Lessons Log
D. Update the product's Product Description with the suggested improvement
What is an objective of a quality review?
A. Determine the quality responsibilities of the project management team
B. Agree the quality method that will be applied to a product
C. Formulate ideas on how the product will be developed
D. Provide consultation with a range of key interested parties regarding a product's quality
Which of the following is a specific quality review team role?
A. User
B. Approver
C. Reviewer
D. Project Support
Which of the following is a quality review team role?
A. Producer
B. Approver
C. Administrator
D. Project Manager
Which of the following is a quality review team role?
A. Project Assurance
B. Producer
C. Chair
D. Quality Assurance
Which of the following is a prioritized list of measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders?
A. Acceptance criteria
B. Quality criteria and tolerances
C. Quality and approval records
D. Customer's quality expectations
Once a product has been completed, from whom would the Team Manager get approval for its completion?
A. Project Manager
B. The authority defined in the product's Product Description
C. Quality Assurance as part of their independent audits
D. The producer of the product
Who carries out checks independent of the project to ensure that the processes are in place for quality planning and control?
A. Project Board
B. Project Assurance
C. Quality Assurance
D. Project Support
What is NOT a purpose of the End Stage Report?
A. Allow the Project Board to decide what to do next with the project
B. Help decide whether to amend the project scope, or stop the project
C. Escalate a stage-level tolerance threat to the Project Board
D. Give a summary of progress to date
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.