What product is reviewed by the Project Manager as part of progress assessment to determine whether a Work Package is performing to the agreed cost and time tolerances?
A. Highlight Report
B. Checkpoint Report
C. Exception Report
D. Off-specification
Are the following statements regarding quality control true or false?
1.
Includes identifying ways to eliminate causes of unsatisfactory performance
2.
Involves defining the products required, their quality criteria and the relevant quality methods
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Both 1 and 2 are false
Which product would document any unfinished work, ongoing issues and risks?
A. Project closure notification
B. Lessons Report
C. End Project Report
D. Risk Register
What is produced by the Project Manager to define and keep control of the work to build products?
A. Product Status Account
B. Checkpoint Report
C. Highlight Report
D. Work Package
Are the following statements regarding raising exceptions true or false?
1.
If the stage is forecast to exceed its tolerances, the Project Manager should produce an Issue Report to capture and analyze the details of the deviation
2.
Where a Work Package is forecast to exceed its tolerances, the Project Manager may request the Team Manager to produce an Exception Plan
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Both 1 and 2 are false
Which product, produced by the Project Manager, would contain information on 'products completed during the period'?
A. Product Status Account
B. Checkpoint Report
C. Highlight Report
D. Exception Report
Which of the following is mandatory in a PRINCE2 project?
A. Use of a separate person as Team Manager
B. Use of management stages
C. Use of Exception Plans
D. Use of Team Plans
Which management level uses the mechanisms included within the Progress theme to control any unacceptable deviations?
A. Only the Project Board
B. Only the Project Manager
C. All levels of management
D. Only corporate or programme management
What name is given to the permissible deviation allowed above and below a plan's target for time and cost without escalating the deviation to the next level of management?
A. Concession
B. Tolerance
C. Project Issue
D. Off-specification
Which of the following is a Project Board control?
A. Approving a deviation of benefits tolerance
B. Approve a Plan, with its relevant tolerances for the next management stage
C. Review Checkpoint Reports to monitor progress
D. Use of project registers and logs to review progress
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.