Which statement about the Directing a Project process is true?
A. Provides a mechanism for the Project Board to assure that there is continuedbusiness justification
B. Covers the day-to-day activities of the Project Manager
C. Ensures there are regular progress meetings
D. Begins on completion of the Initiating a Project process
Why is it crucial that the Project Product Description clearly defines acceptance methods?
A. Enables Project Assurance to authorize quality activities
B. Defines how all project products will be reviewed and approved
C. Defines how it will be proven that the completed project product meets the customer's expectations
D. Provides confirmation that all project products have met their quality criteria
Which is a true statement about PRINCE2 event-driven controls?
A. Event-driven controls take place at predefined periodicintervals
B. Event-driven controls are produced at the frequency defined in a Work Package
C. Event-driven controls are used for decision making
D. Checkpoint Reports are event-driven controls
Which is a purpose of an End Project Report?
A. Identify individuals or groups that need to be told that the project is coming to an end
B. Review how well the project performed against the Project Initiation Documentation used to authorize it
C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
D. Ensure that key project information is archived and made secure
Which is an objective of the Initiating a Project process?
A. Develop the corporate quality management system as part of the Project Initiation Documentation
B. Prepare the plans for the subsequentstages
C. Summarize how the organization's project management method will be tailored for the project
D. Request authority from corporate management to deliver the project
What product records any time tolerances agreed between the Project Manager and Team Manager?
A. Product Description
B. Work Package
C. Project Initiation Documentation
D. Stage Plan
What theme defines and implements the means by which the project will verify that products meet business requirements?
A. Business Case
B. Change
C. Progress
D. Quality
Identify the missing words in the following sentence.
Configuration management typically includes [ ? ] as one of the five core activities.
A. exception planning
B. risk assessment
C. stakeholder engagement
D. status accounting
Which is a purpose of the Closing a Project process?
A. Authorize the final stage of the project
B. Confirm that all benefits defined in the Business Casehave been achieved
C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
D. Delegate day-to-day management of the end of the project to the Project Manager
Which is performed as part of the recommended risk management procedure?
A. Allocation of a budget to investigate issues facing the project
B. Review of risk management practices to ensure that they are performed effectively
C. Sending of information about risks tothe project to project stakeholders
D. Resolution of conflicts between the project and the programme board
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.