Which of the following describes a use of a Configuration Item Record?
A. To record how changes to a product will be controlled
B. To provide information on theapproval procedure for the Work Package
C. To record the history of a product
D. To pass responsibility for the delivery of a product to a Team Manager
What product is used to maintain a record of those who have an interest in the project and their information requirements?
A. Project Plan
B. Communication Management Strategy
C. Project Brief
D. Project Product Description
Which is a purpose of the Directing a Project process?
A. Create and authorize the project mandate
B. Ensure that work on products allocated to the team is authorized and agreed
C. Control the day-to-day running of the project
D. Delegate day-to-day management of the project to the Project Manager
What is described as an organization's unique attitude towards risk taking?
A. Risk appetite
B. Risk management
C. Risk evaluation
D. Risk tolerance
Why would the Project Manager escalate an issue to the Project Board?
A. The Project Board is responsible for determining the priority of all issues
B. Direction is required on the best response for preventing the issue from occurring
C. The issue is forecast to cause a deviation beyond stage tolerance and advice is required
D. Escalating issues is a means of providing the Project Board with a regular update on their status
Why does PRINCE2 recommend three different levels of plans?
A. To cover initiation, specialist work and exception situations
B. To provide appropriate detailto each of the different levels of management within the project
C. As an allowance for initiation, product delivery and project closure
D. To match the different aspects of the product-based planning technique
Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.
A. Corporate or programme management
B. Project Board
C. Team Managers
D. Project Support
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
Which product is used by the Project Manager to authorize work?
A. Team Plan
B. Stage Plan
C. Work Package
D. Product Description
Which is a purpose of a Lessons Log?
A. Note any lessons that are raised in Checkpoint Reports
B. Record that corrective action is being taken
C. Escalate lessons to the Project Board
D. Raise improvements with Project Assurance
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.