Which is a purpose of a Lessons Report?
A. Improve the project management method for future projects
B. Detail open issues and risks that need to be managed after the project has closed
C. Compare the actual performance of the final stage against its plan
D. Provide a summary of the benefits realized during the project
Which is a purpose of the Starting up a Project process?
A. Prevent poorly conceived projects from ever being initiated
B. Ensure the communication requirements of all stakeholders are documented
C. Learn lessons from this project
D. Document how changes required by corporate or programme management will be reviewed
During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?
A. Benefits Review Plan
B. Product Status Account
C. Business Case
D. Project Plan
Which should be funded from a change budget?
A. The Starting up a Project process
B. A fallback plan
C. An agreed change to the scope of a project
D. A change to a plan, within allocated tolerances, due to poor estimating
What is the collective name for individuals or groups who may be affected by a project?
A. Customers
B. Project Support
C. Stakeholders
D. Team members
Which statement applies to Stage Plans?
A. Always have the same duration as the Project Plan
B. Are produced at the same time as the Project Initiation Documentation
C. Assist the Project Manager inthe day-to-day running and control of the project
D. Provide a baseline against which the Project Board monitor overall progress
Which is one of the three levels of plan in PRINCE2?
A. Benefits Review Plan
B. Programme Plan
C. Team Plan
D. Project Brief
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
A. Product Description
B. Team Plan
C. Work Package
D. Stage Plan
Which is a purpose of a Risk Register?
A. Capture risks that may occur during the project
B. Record how risk management activities will be undertaken on the project
C. Record the risk tolerance for the project
D. Capture issues which are impacting on the delivery of the project objectives
Where should the names of those who are to approve a product be recorded?
A. Product Status Account
B. Product Description
C. Configuration Item Record
D. Checkpoint Report
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.