Which of the following are objectives of the Directing a Project process?
1.
Ensure corporate or programme management has an interface to a project
2.
Ensure that work on products allocated to a team is authorized
3.
Ensure there is authority to initiate a project
4.
Ensure that a project remains viable
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Which is created during the Starting up a Project process?
A. Project mandate
B. Project management team role descriptions
C. Communication Management Strategy
D. Quality Register
What is a purpose of a Benefits Review Plan?
A. Provide information regarding unfinished work to the group which will support the project's products in their operational life
B. Give a detailed analysis of only those benefits that were realized before the project closed
C. Document the justification for undertaking the project, based on the estimated costs versus the anticipated benefits
D. Provide details of the time and effort needed to carry out the planned benefits reviews
Which is NOT a benefit of using PRINCE2?
A. Defines specific leadership, motivational skills andother interpersonal skills required
B. Can be applied to any type of project
C. Promotes learning and continuous improvement
D. Defines a thorough but economical structure of reports
Which is a true statement about management stages and technical stages?
A. Technical stages can overlap but management stages CANNOT
B. Management stages are the responsibility of the Project Manager, technical stages are NOT
C. Technical stages create products, management stages do NOT
D. Management stages require quality control, technical stages do NOT
What process provides the information required to decide whether to authorize the delivery of a project?
A. Directing a Project
B. Initiating a Project
C. Managing Product Delivery
D. Starting up a Project
Which is a purpose of the Controlling a Stage process?
A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
B. Provide a fixed reference point at which acceptance for the project product is confirmed
C. Enable the Project Board to be provided with sufficient information to authorize the next stage
D. Enable the organization to understand the work that needs to be done to deliver the project's products
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,
A. producing an achievable Project Plan
B. preventing poorly-conceived projects from ever being initiated
C. obtaining approval from all stakeholders
D. setting up the required project controls
Which enables the project's products and all interdependencies to be clearly identified and documented?
A. Product breakdown structure
B. Quality Management Strategy
C. Product-based planning technique
D. Quality review technique
What is used to identify any organization or interested party who needs to be informed of project closure?
A. Configuration Management Strategy
B. Project management team structure
C. Communication Management Strategy
D. Project Brief
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.