Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
Which is a valid statement about the Project Support role?
A. Can be performed by the Project Manager
B. Is an optional role for a PRINCE2 project
C. Produces Checkpoint Reports for the Project Manager
D. Can be combined with the Project Assurance role
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
A. Raise a request for change
B. Raise an off-specification
C. Write an Exception Report
D. Amend the Work Package
Which is a purpose of the Risk theme?
A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problemsthat have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks
Which role is responsible for specifying the project benefits?
A. Corporate or programmemanagement
B. Executive
C. Senior User(s)
D. Project Manager
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
A. Project Manager
B. Executive
C. corporate or programme management organization
D. Suppliergroups
Which is an objective of the Controlling a Stage process?
A. Prepare a Stage Plan for the next stage
B. Obtain approvals for completed products
C. Prevent scopecreep' by monitoring products for uncontrolled change
D. Make arrangements to address all open issues and risks, with follow-on action recommendations
Which is a benefit of using PRINCE2?
A. Is a method specifically designed for technical projects
B. Provides for the efficient and economic use of management time
C. Includes many of the proven planning techniques, such as critical path analysis
D. Can be used tomanage both projects and programmes
Which is an objective of the Managing a Stage Boundary process?
A. Understand what has gone well and what can help the next stage
B. Review and approve the next Stage Plan
C. Assure the Project Board that all project products have been completed and approved
D. Prepare an Exception Report to advise the Project Board of aforecast deviation from tolerance
Who represents the three project interests on a project?
A. Project Manager
B. Project Support
C. External project stakeholders
D. Project Board
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.