Exam Details

  • Exam Code
    :PRINCE2-FOUNDATION
  • Exam Name
    :PRINCE2 Foundation
  • Certification
    :PRINCE2 Certifications
  • Vendor
    :PRINCE2
  • Total Questions
    :1158 Q&As
  • Last Updated
    :Apr 13, 2025

PRINCE2 PRINCE2 Certifications PRINCE2-FOUNDATION Questions & Answers

  • Question 461:

    Which is a type of issue?

    A. An expected dis-benefit

    B. An off-specification

    C. A project outcome

    D. A scope tolerance

  • Question 462:

    Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

    A. Change

    B. Cross-functional

    C. Unique

    D. Risk

  • Question 463:

    What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?

    A. The preference of the Project Manager

    B. Having insufficient authority to perform the role

    C. Having insufficient time to perform the role

    D. The need to involve key stakeholders on the project management team

  • Question 464:

    Which process is used by a Team Manager to coordinate work on one or more of the project's products?

    A. Initiating a Project

    B. Controlling a Stage

    C. Managing a Stage Boundary

    D. ManagingProduct Delivery

  • Question 465:

    Which is a purpose of the Managing a Stage Boundary process?

    A. Provide the Project Board with sufficient information for approving the next stage

    B. Approve the next Stage Plan

    C. Review and close any risks and issues identified during the previous stage

    D. Control the link between the ProjectManager and the Team Manager(s)

  • Question 466:

    Which of the following take place before the initiation of a project?

    1.

    Appoint the Executive

    2.

    Capture requirements

    3.

    Develop the Project Brief

    4.

    Develop the detailed Business Case

    A. 1, 2, 3

    B. 1, 2, 4

    C. 1, 3, 4

    D. 2, 3, 4

  • Question 467:

    What product should be used to confirm the version number of ail products in a particular stage?

    A. Issue Register

    B. Product Status Account

    C. Product Description

    D. Configuration Item Record

  • Question 468:

    Which is an objective of the Starting up a Project process?

    A. Approve allProduct Descriptions prior to project initiation

    B. Obtain approval from corporate or programme management for the Communication Management Strategy

    C. Prevent projects with unrealistic delivery dates from being initiated

    D. Confirm that there is a validmethod in place to measure the expected project benefits

  • Question 469:

    In what product should the quality criteria for a specialist product be recorded?

    A. Quality Management Strategy

    B. Quality Register

    C. Product Description

    D. Project Product Description

  • Question 470:

    Which is a purpose of a Project Brief?

    A. Enable the assembly of the project mandate

    B. Describe the reporting requirements of the various layers of management involved with the project

    C. Describe how changes to products will be controlled

    D. Provide a solid basis for the initiation of the project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.